SEEPAGE ANALYSIS AND SAFETY EVALUATION OF JLT HYDROPOWER STATION DAM

机译:JLT水电站大坝渗流分析及安全评价

获取原文

摘要

The maximum dam height of JLT Hydropower dam is 157 m. The seepage discharge measured by measuring weir after water impoundment is large. Based on the analysis of seepage reason and developing trend, the seepage will only result in a little electricity loss and have no threat to the dam body, dam foundation and the two banks. The design of hydraulic structure seepage control is discussed in the paper.