This paper discusses a major construction project at St. Louis-Lambert International Airport where a new parallel runway with two taxiways was constructed as part of the airport expansion. The paper focuses on the geotechnical aspects of the project, which included time issues (construction expedients), use of chemical additives, slope stability, settlement, and subgrade stabilization. One of the unique challenges of the project was that cuts and fills of up to 30 meters were made as part of the grading for the runway platform and involved moving approximately 12 million cubic meters of soil. In addition, the cut was almost entirely below the groundwater table. The project also involved construction of the first highway tunnel in the state of Missouri.
机译:本文讨论了圣路易斯 - 兰伯特国际机场的主要建筑项目,其中建造了两个滑行道的新平行跑道作为机场扩张的一部分。本文重点介绍该项目的岩土工程,其中包括时间问题(施工权宜之计),使用化学添加剂,边坡稳定性,沉降和路基稳定。该项目的独特挑战之一是,削减和填充最多30米,作为跑道平台等级的一部分,并涉及移动约1200万立方米的土壤。此外,切割几乎完全在地下水位下方。该项目还涉及密苏里州第一道公路隧道的建设。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号