Outage management improvements in Nuclear Electric

机译:核电中的中断管理改进

获取原文
获取外文期刊封面目录资料

摘要

The drive for a more efficient nuclear power industry has been the force behind major improvements in many key areas of business over the last few years, none more so than in power station statutory outages. Developments in the way that outages are approached and managed, with a significant emphasis on the enhancement of safety and quality improvements, have brought considerable reductions in outage durations, with advanced gas cooled reactors (AGRs) averaging 150 days in 1990 to 55 days in 1994. Significant improvements continue to be made with the UK's Heysham 2 power station achieving a new AGR outage record of 35 days in 1995 and in 1997 the successful completion of two complex outages requiring major modifications to both reactors and turbines. The author illustrates the reduction in outage durations achieved at Heysham 2. This paper is a case study of the improvements made at Heysham 2 that significantly contributed to that success.
机译:对于一个更高效的核电力行业的驱动器一直是过去几年许多关键业务领域的主要改进的力量,而不是在发电站法定中断。进入和管理中断的发展,重视加强安全性和质量改进,在1990年的1990年的晚期150天内平均150天至55天,对中断持续时间带来了相当大的降低。 。在1995年的英国的Heysham 2电站延续了达到了35天的新农业停电记录,1997年成功完成了两种复杂的停电,需要对电抗器和涡轮机进行重大修改的成功完成。作者说明了Heysham 2.在Heysham 2上取得的中断持续时间的减少。本文是对Heysham 2所做的改进的案例研究,这显着促成了这一成功。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号