首页> 外文会议>International Pipeline Conference >HOT BITUMEN PIPELINE VALVE REPLACEMENT: PIPE PROP ANCHORING DESIGN WITH MECHANICAL TENSIONING
【24h】

HOT BITUMEN PIPELINE VALVE REPLACEMENT: PIPE PROP ANCHORING DESIGN WITH MECHANICAL TENSIONING

机译:热沥青管道阀门更换:管道支柱锚固设计,机械张紧

获取原文

摘要

An NPS 24 inline gate valve on a buried hot bitumen pipeline operating at temperatures up to 149°C failed open. The valve is on the north bank of the Steepbank River in northern Alberta and is equipped with an actuator that can automatically close the valve to protect the river in case of an emergency. It was therefore important to replace the valve as soon as practical. Worley was engaged to provide detailed engineering services for replacing the valve. Engineering objectives covered safety concerns associated with high operating temperatures and large axial compressive force in the pipeline, minimization of downtime, development of the best long-term valve replacement solution, and return of the pipeline to service with the same resistance to upheaval buckling it had when it was originally designed and constructed. Because the pipeline is buried and therefore restrained by the surrounding soil, an important goal of the original design was to prevent upheaval buckling and possible loss of containment by controlling thermal expansion forces due to its high operating temperature. Control was achieved during the original construction in two ways. Firstly, thermal compressive forces were reduced by heating the line to 90°C with forced air and locking it into the surrounding soil in its expanded state, and secondly, restraint was increased by using good backfill compaction, increased depth of burial, and imported fill wherever necessary. The high axial compressive force on the inline buried valve was identified as a possible cause of failure, and an early decision was made to replace it using an aboveground valve with sufficiently flexible aboveground piping to minimize or eliminate compressive forces on the valve. When the pipeline was cooled and cut to install the new valve, the original prestress was released, and the cut ends of the pipe pulled back on either side of the valve. The lost prestress was reinstated to the level specified in the original design using an innovative custom designed load bearing strut and tensioning system, referred to here as a Pipe Prop, that was installed between the cut ends of the buried mainline after the failed valve and fittings had been removed. The Pipe Prop also prevented differential axial movement between the cut ends of the buried pipeline due to changes in the operating pressure and temperature. This reduced the need for flexibility in the aboveground piping and allowed a short offset to be used between the new valve and the buried mainline, which reduced the footprint of the aboveground piping enough to fit within the restrictive boundaries of the site. Strain gauges were installed on the pipeline adjacent to the failed valve and upstream and downstream of the valve site. The gauges measured changes in stress when the buried pipeline was first cut. and allowed the stress state of the buried pipeline to be calculated to find if the cause of failure had been large axial loads imposed on the valve by the pipeline. The strain gauges also measured strain in the buried pipeline while using the tensioning system built into the Pipe Prop to re-establish the design level of prestress. Permanent strain gauges were also installed on the new aboveground piping adjacent to the replacement valve. The pipeline was returned to hotbit service in August 2019 and has operated continuously since that time without further problems at the valve station.
机译:在埋地的热沥青管道上的NPS 24内联闸阀在高达149°C的温度下操作失败。阀门位于艾伯塔北北部的Steebank河北岸,配有一个可以自动关闭阀门以保护河流的执行器,以防紧急情况。因此,尽快更换阀门是很重要的。 Worley订婚,为更换阀门提供详细的工程服务。工程目标涵盖了与管道中高效温度和大型轴向压缩力相关的安全问题,最小化停机时间,最佳的长期阀门更换解决方案的开发,以及返回的管道与其具有相同的抵抗力的服务当它最初设计和构建时。由于管道被埋入并因此受到周围土壤的抑制,原始设计的一个重要目标是通过控制由于其高工作温度控制热膨胀力来防止动膨胀和可能的遏制损失。在原始建筑中以两种方式实现控制。首先,通过用强制空气加热到90℃并将其锁定在其膨胀状态下,通过使用良好的回填压实,增加埋藏和进口填充,增加了热压缩力并将其锁定到周围土壤中,并提高了克制。必要时。内联埋阀上的高轴压压缩力被识别为可能的故障原因,并采用早期的决定在使用足够柔性管道上使用地上阀门更换它以最小化或消除阀上的压缩力。当管道被冷却并切割以安装新阀门时,释放原始的预应力,管道的切割端向阀的任一侧拉回。使用创新的定制设计负载支柱和张紧系统将丢失的预应力恢复到原始设计中规定的水平,在此称为管道支柱,在失效的阀门和配件故障后安装在埋设主线的切割端之间的管道支柱之间已被删除。由于操作压力和温度的变化,管道支柱也防止了由于工作压力和温度的变化而在掩埋管道的切割端之间的差动轴向运动。这减少了在地上管道中的灵活性的需求,并且允许在新阀和埋设的主线之间使用短偏移,这减少了足够的地上管道的占地面积,以适应该部位的限制性边界。应变仪安装在靠近故障阀和阀部位的上游和下游的管道上。当埋入的管道首次切割时,仪表测量了应力的变化。并允许掩埋管道的应力状态来计算以找到故障原因是否通过管道在阀门上施加的大轴向载荷。应变仪在埋入管道中测量应变,同时使用内置在管道支柱中的张紧系统来重新建立预应力的设计水平。在与替换阀相邻的新地上管道上也安装了永久性应变仪。 2019年8月,管道被返回到Hotbit Service,并从那时起不断运营,因为阀门站没有进一步的问题。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号