5 Drives with 26 Curves Built in Zug, Switzerland; Lessons Learned

机译:在瑞士楚格(Zug)建有5条26条曲线的驱动器;得到教训

获取原文

摘要

The sewer system in the city of Zug, Switzerland is finished with a new surface water discharge line of 79 inch inner diameter consisting of 3 microtunnels with lengths of 2,894 feet, 1,932 feet and 1,187 feet. Further on the city planned to use the lake’s water for heating and cooling purposes, which requires 2 additional 63 inch inner diameter drives which run next to the surface water line in a distance of as little as 4 feet. These 5 drives were built with 8 vertical and 18 horizontal curves to get around the obstacles in the ground and to place shafts at the least disturbing locations. All drives are located under roads with heavy traffic in the middle of the inhabited city.The construction period for the drives was from September 2017 to May 2018 including 2 stops and rescue pits. The tunneling work was carried out 24 hours a day, 7 days a week. This to keep the disabilities in the city center as short as possible.As a result of the size of the project, the boundary conditions and the very tight deadlines for execution planning and implementation, new tasks were constantly arising. This paper discusses the lessons learnt through designing and executing by the perspective of an engineer. Risk management, rolling planning, ensuring the required quality, cost monitoring and cost forecast, time schedule and technical challenges are the main points. The lecture should inform about risks and mistakes and give recommendations for upcoming projects.
机译:瑞士楚格(Zug)市的下水道系统完成了一条内径为79英寸的新地面排水管线,该管线由3个微隧道组成,长度分别为2,894英尺,1,932英尺和1,187英尺。在计划将湖水用于供暖和降温的城市中,还需要另外2个63英寸内径驱动器,该驱动器与地表水管线相邻,相距仅4英尺。这5个驱动器具有8个垂直和18个水平曲线,可绕过地面上的障碍物并将轴放置在干扰最小的位置。所有驱动器都位于居住城市中间交通繁忙的道路下面。 该驱动器的建设期为2017年9月至2018年5月,包括2个停靠站和救援站。每周7天,每天24小时进行隧道作业。这样可以使残障人士在市中心的时间尽可能短。 由于项目规模,边界条件以及执行计划和实施的紧迫期限,新任务不断出现。本文讨论了从工程师的角度通过设计和执行所获得的经验教训。重点是风险管理,滚动计划,确保所需质量,成本监控和成本预测,时间表和技术挑战。讲座应告知风险和错误,并为即将进行的项目提供建议。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号