Seattle Public Utilities (SPU) completed emergency design and construction of an 1160 foot-long 16-inch OD HDPE sewer beneath Shilshole Bay Waterway in the Ballard area of Seattle using horizontal directional drilling (HDD). Staheli Trenchless Consultants served as designer and provided specialty inspections during construction on the WWPS43 Emergency Force Main Replacement Project. This paper presents the case study of the project, lessons learned, and evaluation of the data collected during construction.In 2017, SPU discovered a severe leak in an existing cast iron force main discharging sewage into the Shilshole Bay Waterway, the canal leading from Puget Sound to Lake Washington and a USACE governed waterway. To mitigate the concern of leaking sewage, three months of 24-7 emergency response consisting of extensive pump and truck bypassing was undertaken to remove flow and leakage from the pipe. An above-ground temporary bypass was constructed, and given the risk of impending combined sewer overflows, the force main full-line replacement project was given emergency design and construction status. During pre-design efforts, HDD trenchless technology was determined as the least risk, most cost-effective method to install a replacement sewer line.The project required extensive coordination with many federal, state, and local permitting agencies, including: USACE, NMFS, USFWS, DAHP, DNR, WDFW and other organizations. The project encompassed sensitive communities on both sides of the waterway, one near a very popular biking and walking path - the Burke Gilman Trail. Furthermore, the design had to balance coordination with two active rail lines, adjacent construction projects, multiple property owners and construction fatigue in the surrounding neighborhoods.
机译:西雅图公用事业(SPU)完成了Shilshole Bay Waterway的1160英尺长的16英寸OD HDPE下水道的紧急设计和建设,使用水平定向钻孔(HDD)。 Staheli Tronchless顾问作为设计师,并在WWPS43紧急力主要更换项目施工期间提供了专业检查。本文提出了对项目,经验教训的案例研究,以及在建设期间收集的数据的评估。2017年,SPU在现有的铸铁力量主要净化污水中发现了严重泄漏,该污水进入Shilshole Bay Waterway,这是从普吉特声音到华盛顿湖和一座USACE治理水路的运河。为了减轻泄漏污水的关注,三个月的24-7应急响应由广泛的泵和卡车旁路组成,以除去管道的流量和泄漏。构建了上面的临时旁路,并赋予迫使下水道溢出的风险,强制主要全线更换项目得到应急设计和施工状态。在预设计工作期间,HDD挖掘技术被确定为最少的风险,最具成本效益的方法来安装更换下水道线。该项目要求与许多联邦,州和地方许可机构进行广泛的协调,包括:USACE,NMFS,USFW,DAHP,DNR,WDFW等组织。该项目包括水道两侧的敏感社区,一个靠近一个非常受欢迎的自行车和步行道 - 伯克吉尔曼小径。此外,该设计必须与周围社区的两个主动轨道线,相邻的建筑项目,多个物业所有者以及施工疲劳进行平衡。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号