Construction of a Deep Cutoff Wall along the Mississippi River at East Alton, IL

机译:在East Alton,IL的密西西比河沿着密西西比河深截止墙建造

获取原文

摘要

The confluence of the Wood River and the Mississippi River, in East Alton, Illinois, has been plagued with seepage under Lower Wood River Levee to the point that remediation was needed. The Southwestern Illinois Flood Prevention District Council enlisted experts to evaluate, design and construct under-seepage controls. The selected design required the construction of a cement-bentonite cutoff wall, 140 feet deep, excavated through alluvial and outwash soils and embedded in bedrock. The unique aspect of this project was that the cutoff wall was installed using a hydromill cutter under self hardening slurry (SHS), to a depth that had not been reached using this method in past cutoff walls constructed in the United States. The quality control/quality assurance (QC/QA) testing was comprehensive throughout the entire process. This paper will give an overview of the project and a summary of the test results.
机译:伊利诺伊州东奥尔顿的木河和密西西比河的汇合已经困扰着下木河堤渗出到需要修复的地步。伊利诺伊州西南部防洪区议会招募专家评估,设计和构建渗透控制。所选择的设计需要构建水泥 - 膨润土截止墙,140英尺深,通过冲积和露出土壤挖掘,并嵌入基岩中。该项目的独特方面是使用自硬化浆料(SHS)下的液体刀具安装截止墙,以在美国建造的过去的截止墙上使用该方法达到的深度。在整个过程中,质量控制/质量保证(QC / QA)测试是全面的。本文将概述该项目的概述和测试结果的摘要。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号