Repair of Subgrade Failure During a 104-Hour Track Window BNSF Railway Little Falls, Minnesota

机译:明尼苏达州BNSF铁路Little Falls 104小时跟踪窗口期间路基故障的修复

获取原文

摘要

BNSF Railway recently completed an expedited repair of a significant subgrade failure beneath a 300-foot section of new 2nd main line track near Little Falls, Minnesota. The subgrade materials in the area of track distress were comprised of a 3-foot thick shot rock stabilized subgrade underlain by relatively deep, soft organic clays and peat extending to depths of 5 to 18 feet below bottom of tie. Repair options evaluated included 1) an at-grade land bridge, 2) compaction grouting, 3) soil mixing and 4) a column-supported load transfer platform (LTP). The column-supported LTP was chosen for track support in the identified zone of distress due to its cost, flexibility, and speed of installation. Helical piles were used as the columns because conventional driven pile were anticipated to have driving difficulties through the shot rock section, which would likely require predrilling. The LTP for the new 2nd main line repair was completed during a 104-hour continuous track window in which 480 feet of track and 1,100 cubic yards of ballast/subballast and embankment were removed; then 256 helical piles, a 30-inch LTP and subballast/ballast were installed prior to replacement of the track. The repair activities were completed without injuries and on time despite initially inclement weather. No further track movement has been observed since the LTP installation. This paper discusses the original construction, observed distress, geotechnical investigation and design of the LTP, as well as summarizes the lessons learned during the construction activities.
机译:BNSF铁路公司最近完成了对明尼苏达州利特福尔斯附近新的第二条主线轨道300英尺段下方重大路基故障的快速维修。轨道遇险区域的路基材料包括一个3英尺厚的喷丸稳定路基,该路基由相对较深的柔软有机粘土和泥炭覆盖,并延伸到连接底部以下5至18英尺的深度。评估的维修方案包括:1)一座平地桥,2)压实灌浆,3)土拌和和4)立柱支撑的荷载传递平台(LTP)。由于其成本,灵活性和安装速度,选择柱支撑的LTP作为在确定的遇险区域中的轨道支撑。螺旋桩被用作立柱,是因为传统的打入桩在穿过抛石段时会遇到驱动困难,这可能需要预先钻探。新的第二条主干线维修的LTP在104小时的连续轨道窗内完成,其中移除了480英尺的轨道和1,100立方码的压载/副压载物和路堤;然后在更换轨道之前,先安装256个螺旋桩,30英寸LTP和镇流器/镇流器。尽管起初天气恶劣,但维修工作已按时完成,没有受伤,仍能按时完成。自从安装LTP以来,没有观察到任何进一步的轨道运动。本文讨论了LTP的原始施工,观察到的遇险,岩土勘察和设计,并总结了在施工活动中汲取的经验教训。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号