CITY OF SASKATOON TRANSPORTATION UTILITIES DEPARTMENT 2014 WATER REHABILITATION PROGRAM

机译:2014年萨斯卡通市交通与公用事业局水修复计划

获取原文
获取外文期刊封面目录资料

摘要

The 2014 Water Rehabilitation project consisted of 2 projects, (Table 1), East & West, within the City of Saskatoon,Saskatchewan Canada.The referenced project was the largest single contract, at the time of tender, let in North America to rehabilitateexisting water mains using a Cured-in-Place Pipe (CIPP) lining system designed specifically for drinking water.A number of project conditions presented many challenges during the installation of the CIPP lining systems. Thisincluded site excavation, installing and maintaining the temporary by-pass water / conveyance system, conflictsbetween various underground and aged utilities, repairs of sections of the sanitary sewer system that conflicted withnew installations, depths of the water mains, site rental days, cleaning the mains, traffic control, weather, andmanaging and tracking of change orders. Additional challenges included finding and hiring skilled workers toperform the work. Recently the Canadian Government changed the process for allowing US skilled workers to enterand work in Canada during the course of the project which changed the planning for the work performed in yeartwo. The General Contractor (Michels Canada Co.) had to replace a local civil subcontractor used during year oneof the project due to various issues, such as safety violations and mismanagement of their work. Michels Canadachose to self-perform the civil portion of the project in year two.The use of trenchless technology was the primary driver of the project. The Owner determined the aginginfrastructure needed to be rehabilitated over a 5 year program and chose CIPP as the best option. The lining systemselected was Sekisui’s NordiPipe lining system for drinking water. This system is a fully structural Class IV liningsystem per AWWA, M-28 Manual (AWWA, 2014).
机译:2014年的水资源修复项目包括萨斯卡通市内的东西方两个项目(表1), 加拿大萨斯喀彻温省。 引用的项目是招标时最大的单个合同,让其在北美进行修复 现有的水管使用专门为饮用水设计的现浇管(CIPP)衬里系统。 在安装CIPP衬砌系统期间,许多项目条件提出了许多挑战。这 包括现场开挖,安装和维护临时旁路水/输送系统,冲突 在各种地下和老旧公用事业之间进行维修,对与污水处理厂相冲突的下水道系统进行修复 新装置,水管深度,工地租赁天数,清洁水管,交通控制,天气和 管理和跟踪变更单。其他挑战包括寻找和雇用熟练工人 执行工作。最近,加拿大政府改变了允许美国技术工人进入的程序 在项目过程中在加拿大的工作,这改变了当年进行的工作的计划 二。总承包商(加拿大米歇尔公司)必须更换第一年使用的当地民用分包商 由于各种问题(例如违反安全性和对工作的管理不当)而导致该项目无法正常运行。加拿大米歇尔 选择在第二年自行执行项目的土建部分。 使用非开挖技术是该项目的主要推动力。业主确定了账龄 需要在五年计划中修复基础架构,并选择CIPP作为最佳选择。衬里系统 选择的是积水的NordiPipe饮用水衬里系统。该系统是完全结构的IV级衬里 系统根据AWWA,M-28手册(AWWA,2014年)进行。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号