Foundation Designs for a 345 kV Transmission Line Constructed in the Lakebed of Glacial Lake Agassiz

机译:冰河阿加西兹湖床修建的345 kV输电线路的基础设计

获取原文

摘要

The Fargo - Saint Cloud 345 kV transmission line project led by Xcel Energy as part of the CapX2020 transmission expansion initiative includes about 52 miles containing 284 tubular steel structures located in the lakebed of Glacial Lake Agassiz (GLA) in northwest Minnesota and eastern North Dakota. GLA was an immense glacial lake. It was larger than all of the Great Lakes combined and held more water than all lakes in the world today. When GLA drained about 8,500 years ago, it left deep soft clay deposits that can create a challenge for foundation installation and can introduce potential for long-term creep in foundation deflections. A study, which included full scale constructability testing, was conducted to evaluate appropriate design and construction methods to address these concerns. This paper will describe the study and the design and construction methods used to install foundations in the deep soft clay deposits of GLA.
机译:作为CapX2020输电扩展计划的一部分,由Xcel Energy牵头的Fargo-Saint Cloud 345 kV输电项目包括位于明尼苏达州西北部和北达科他州东部的冰川阿加西兹湖(GLA)湖床中的约284英里,其中包含284个管状钢结构。 GLA是一个巨大的冰川湖。它比所有五大湖之和大,拥有的水量超过当今世界上所有湖泊的总和。当GLA大约在8500年前排水时,它留下了深层的软粘土沉积物,这给基础安装带来了挑战,并可能在基础挠度中带来长期蠕变的可能性。进行了一项包括全面建造性测试的研究,以评估适当的设计和建造方法来解决这些问题。本文将介绍在GLA深层软粘土矿床中安装地基的研究以及设计和施工方法。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号