1. Diesel generator provided power to critical loads 2. PV was unavailable 3. 250kW Load Bank used to test diesel generator; energy dissipated as heat. 1. Baseline Peak Demand = 305kW. 2. Microgrid Peak Demand = 261 kW (14.4% reduction). 3. Use of PV array in microgrid mode reduced diesel fuel consumption and GHG by over 20%. 4. Microgrid maintained critical load of 30-50kW (80kW peak) 5. Stable voltage, frequency and power factor when islanded. 6. Some issues with transient power when PV dropped rapidly. 7. Microgrid maintained power factor > 0.9 when grid connected. 8. Simulated energy arbitrage, but cycle life of battery a concern. 9. Savings to Investment Ratio > 1.5 when scaled for BCT with 4.5MW peak load (9 year payback using NIST BLCC). 10. Follow-on: Integrate another battery system (EW-201404).
机译:1.柴油发电机组为关键负载供电2.光伏不可用3. 250kW负载箱用于测试柴油发电机组;能量以热量的形式消散。 1.基线峰值需求= 305kW。 2.微电网峰值需求= 261千瓦(减少14.4%)。 3.在微电网模式下使用光伏阵列可将柴油燃料消耗和温室气体减少20%以上。 4.微电网维持30-50kW(峰值80kW)的临界负载。5.孤岛时,电压,频率和功率因数稳定。 6. PV迅速下降时瞬态功率的一些问题。 7.并网时,微电网的功率因数> 0.9。 8.模拟了能量套利,但是电池的循环寿命值得关注。 9.当以4.5MW峰值负荷(使用NIST BLCC的9年投资回收期)进行BCT扩展时,储蓄投资比率> 1.5。 10.后续:集成另一个电池系统(EW-201404)。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号