Insights from the SM2A pilot study towards quantification of a change of plant safety margin after a hypothetical power up-rate

机译:SM2A试验研究探讨了在假设的电动率后朝向植物安全裕度变化的量化

获取原文

摘要

During recent years, many nuclear power plants underwent significant modifications, e.g. power up-rating. While compliance with all the deterministic acceptance criteria must be shown during the licensing process, the larger core inventory and the facts that the plant response might get-closer to the limits after a power up-rate, suggest an increase of the core damage frequency (CDF) and other possible risk indicators. Hence, a framework to quantitatively assess a change in plant safety margin becomes very desirable. The Committee on the Safety of Nuclear Installations (CSNI) mandated the Safety Margin Action Plan expert group (SMAP) to develop a framework for the assessment of such changes to safety margin. This framework combines PSA and the analytical techniques developed in BEPU. CSNI then mandated the SM2A expert group to especially explore the practicability of the SMAP framework. This pilot study was completed end of 2010. An increase of the (conditional) probability of exceedance for a surrogate acceptance limit (PCT) indicating core damage was successfully evaluated for the selected sequences from several initiating event trees, and it was found that only a restricted number of sequences need to be analyzed. The impact of power up-rate could also be assessed for scenarios where no violation of the surrogate criterion was observed. The modeling of human actions was found to be of particular importance as the sequences related to scenarios including a time delay for a recovery action or for a repair correspond to the more visible risk increase.
机译:近年来,许多核电站经历了显着的修改,例如,上电。虽然必须在许可过程中遵守所有确定性验收标准,但核心库存的较大核心库存和植物反应可能更接近电压后的限制,建议增加核心损伤频率( CDF)和其他可能的风险指标。因此,定量评估植物安全裕度变化的框架变得非常可取。核设施安全委员会(CSNI)授权安全保证金行动计划专家组(SMAP),为评估安全保证金进行评估框架。该框架结合了PSA和BEPU中开发的分析技术。然后CSNI要求SM2A专家组特别探索SMAP框架的实用性。这项试验研究已完成2010年底。(条件)超越替代验收限制(PCT)的增加概率,表明核心损坏的核心损坏是针对几种启动事件树的所选序列成功评估,并且发现只有一个需要分析限制序列数。还可以评估电量上涨率的影响,以便没有观察到违反替代标准的情况。发现人类行动的建模是特别重要的,因为与恢复动作或修复的时间延迟包括延迟的情况,或者对应于更明显的风险增加。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号