首页> 外文会议>Pipeline Division specialty conference;Pipelines 2010 >Lessons from an HDD Project That Was Awarded for $ 1.74 Million with 90 Days to Complete That Took in Excess of $ 6 Million and More Than 1,000 Days
【24h】

Lessons from an HDD Project That Was Awarded for $ 1.74 Million with 90 Days to Complete That Took in Excess of $ 6 Million and More Than 1,000 Days

机译:来自HDD项目的教训,该项目获得了174万美元的奖励,需要90天才能完成,费用超过600万美元且超过1000天

获取原文

摘要

The City and its Engineer bid, during the summer of 2005, about 3,200 ft of 36 inch HDPE pipe for a lake crossing to be installed via Horizontal Directional Drilling (HDD) in order that this water transmission line could be put in service by May 1, 2006. On July 14, 2005 when bids were tabulated, Company X became the lowest bidder at $1,740,000. The second and third lowest bidders were at $ 2,004,053. and $ 2,289,400, respectively. The contract completion date was agreed upon as November 1, 2005 at the pre-construction meeting held on August 16, 2005. The entire, final design and alignment selection were based on only 4 soil borings and no appropriate geotechnical baseline report was ever done or used by the Engineer or their HDD consultant. The driller had so many problems that could have been anticipated even if one of the parties involved in this project spent a few more minutes studying the implications of the 4 soil borings. The author was retained on November 14, 2007, by the law firm representing the driller, to conduct an independent investigation as to the causes that led to the delay and cost overruns on this project after the driller had been at the site for longer than 1,000 days and had spent over $6 million by their estimate. Loss of drilling fluids, caving of roads, settlement of houses, buildings, and other calamities were the outcome that the driller, the engineers and the city faced. The lives of local residents were disrupted for many months. There were many lessons learnt and the author shares many of them with the attendees of this conference in the hope similar problems can be avoided in the future.
机译:纽约市及其工程师竞标,在2005年夏季,通过水平定向钻探(HDD)安装约3200英尺的36英寸HDPE管,用于湖道穿越,以便于5月1日前将这条输水管线投入使用。 ,2006年。2005年7月14日,当出价被制成表格时,X公司成为最低的出价,为$ 1,740,000。第二和第三低的投标人是$ 2,004,053。和$ 2,289,400。合同的完成日期是2005年11月1日在2005年8月16日举行的施工前会议上商定的。整个,最终的设计和路线选择仅基于4个土壤钻孔,并且没有进行过适当的岩土基准报告或由工程师或其硬盘顾问使用。即使参与该项目的一方花了几分钟的时间来研究这4种土壤钻孔的含义,司钻也有许多可以预见的问题。提交人于2007年11月14日被代表司钻的律师事务所聘请,对司钻在现场停留超过1000的原因导致该项目的延误和成本超支的原因进行了独立调查。天,据他们的估计花费了超过600万美元。钻井液,钻井,房屋,建筑物和其他灾害的损失是钻井工人,工程师和城市面临的后果。当地居民的生活被干扰了许多个月。有很多经验教训,笔者与本次会议的与会者分享了许多经验,希望将来可以避免类似的问题。

著录项

相似文献

  • 外文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号