Taxiway Embankment Construction on Soft Ground Using In-situ Instrumentation and Staged Construction

机译:现场仪表和分段施工在软土地上滑行路堤施工

获取原文

摘要

The Piedmont Triad International Airport (PT1A), Greensboro, NC is undergoing an expansion as a result of the construction of a regional hub for Federal Express. Part of the construction includes an embankment over an alluvial floodplain in a wetlands area. A hybrid ground modification technique was used to stabilize the soft ground, consisting of geogrids, wick drains and rock toe berms. An instrumentation program was implemented to evaluate the changing properties of the alluvial soils, lateral displacements of the embankment foundation soils, settlement of the embankment, determine the fill placement rates or appropriate waiting periods, and to prevent slope failures from occurring. This paper highlights key features of the design and instrumentation system. It describes the project conditions and considerations, the instrumentation system that was installed, the results obtained during construction, and practical issues that were addressed during construction.
机译:由于建设了联邦快递区域枢纽,北卡罗来纳州格林斯伯勒的皮埃蒙特三合会国际机场(PT1A)正在扩建中。该建筑的一部分包括在湿地地区的冲积洪泛区上的路堤。混合地面改良技术用于稳定软土地基,包括土工格栅,灯芯排水管和岩趾护堤。实施了一个仪器程序来评估冲积土的变化特性,路堤基础土的侧向位移,路堤的沉降,确定填筑率或适当的等待时间,并防止发生边坡破坏。本文重点介绍了设计和仪器系统的主要功能。它描述了项目条件和考虑因素,已安装的仪器系统,在施工过程中获得的结果以及在施工过程中解决的实际问题。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号