Sizewell B nuclear power station has a main electrical system that connects together the main turbogenerators, generating at 23.5 kV, the 400 kV grid and the auxiliary equipment required to operate the station. A separate essential 3.3 kV electrical system fed from the main electrical system, supplies all the auxiliaries required to shut-down the nuclear reactor and maintain it in a safe shut-down condition. The function of the load shedding and emergency load sequencing (LSELS) system is to monitor the condition of the 3.3 kV incoming supply from the main electrical system to each essential 3.3 kV switchboard and initiate its replacement, with the supply from an associated diesel standby generator, if it is outside set parameters. Therefore the design of the system must be highly reliable and the purpose of this paper is to detail the design approach used to ensure that a high system reliability is achieved.
机译:Sizewell B核电站的主要电气系统将23.5 kV的主要涡轮发电机,400 kV电网和运行该电站所需的辅助设备连接在一起。由主电气系统供电的独立的基本3.3 kV电气系统可提供关闭核反应堆并将其维持在安全关闭状态所需的所有辅助设备。减载和紧急负载排序(LSELS)系统的功能是监视从主电气系统到每个基本3.3 kV配电盘的3.3 kV输入电源的状况,并通过相关的柴油备用发电机的电源启动其更换,如果它在设置参数之外。因此,系统的设计必须高度可靠,并且本文的目的是详细介绍用于确保实现高系统可靠性的设计方法。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号