Analysis of ground wire fault in the section of incoming lines of electrified railway traction station

机译:电气化铁路牵引站进线段地线故障分析

获取原文

摘要

The paper analyzes reasons for the failure of strain clamp hardware in the power supply line of an electrified railway traction substation, carries out strain clamp material test, grounding current measurement, arc simulation and other relevant tests, and the reasons for the fault are analyzed as follows: the contact surface is narrow between the strain clamp steel anchor and the U-shaped hanging ring because of the connection structure between them, which is likely to result in gap under the influence of vibration and other environment factors, thus giving birth to suspended potential and bringing about arc ablation under the joint effects of voltage, current and environment and melting and fracturing them gradually. The paper also proposes control measures and recommendations against the fracture fault of strain clamp hardware involved in the power supply line at the side of traction substation system. side power supply line of traction substation.
机译:本文分析了电气化铁路牵引变电所供电线路中应变片硬件故障的原因,进行了应变片材料测试,接地电流测量,电弧模拟等相关测试,并分析了故障原因。如下:由于应变夹钢锚与U形吊环之间的连接结构,接触面较窄,在振动和其他环境因素的影响下很可能导致间隙,从而产生悬浮在电压,电流和环境的共同作用下产生电势并引起电弧烧蚀,并使它们逐渐熔化并破裂。本文还针对牵引变电所系统侧电源线中所涉及的应变钳硬件的断裂故障,提出了控制措施和建议。牵引变电站的一侧电源线。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号