首页> 外文会议>Annual highway geology symposium >Remediation of Slope Instability in Presumpscot Marine Clay using Steel H-Piles Mile Brook Bridge over Outlet Stream, Winslow, Maine
【24h】

Remediation of Slope Instability in Presumpscot Marine Clay using Steel H-Piles Mile Brook Bridge over Outlet Stream, Winslow, Maine

机译:在缅因州温斯洛的出口水流上使用钢制H-Piles Mile Brook桥修复前铺海底粘土中的斜坡不稳定性

获取原文

摘要

The new, two-lane, 325-ft long replacement bridge required the approach embankments to be raised by 2 to 4 ft to improve the vertical profile of the roadway. As a result, engineering evaluations were conducted to assess the potential for global stability issues associated with a 40-ft thick layer of soft, marine clay located below the west embankment. The results of these evaluations showed that an approximately 100-ft long portion of the slope had a lower factor of safety than the minimum required by AASHTO LRFD. Several remedial alternatives were considered, including use of lightweight fill to raise embankment grades, construction of embankment retaining walls, installation of slope reinforcing elements, conducting ground improvement and constructing a stabilization berm at the toe of the slope. Alternatives were evaluated based on technical feasibility, cost, environmental impacts and schedule impacts. Slope stabilization piles were determined to be the most cost-effective alternative, in part since pile driving equipment would already be on site to install the west abutment foundation piles. Equally as important, this alternative had the shortest installation time, which was another critical factor as the design-build project schedule developed by Maine Department of Transportation (MaineDOT) was aggressive. Slope stabilization using reinforcement piles had not previously been used by MaineDOT, but the technique has been successfully used on projects outside the State. A total of 32, HP 12×53 piles were installed using a vibratory hammer in four days to stabilize the west approach. This cost-effective and innovative approach played a part in the successful award of this $5.4 million project to the design-build team.
机译:新的两车道,325英尺长的替换桥需要将引路堤抬高2到4英尺,以改善巷道的垂直剖面。结果,进行了工程评估,以评估与位于西堤下的40英尺厚的软质海洋粘土层相关的全球稳定性问题的可能性。这些评估的结果表明,大约100英尺长的斜坡部分的安全系数低于AASHTO LRFD要求的最小值。考虑了几种补救措施,包括使用轻质填料来提高路堤等级,建造路堤挡土墙,安装斜坡加固元件,进行地面改良以及在斜坡脚趾处建造稳定护堤。根据技术可行性,成本,环境影响和进度影响评估替代方案。边坡稳定桩被确定为最具成本效益的替代方案,部分原因是打桩设备已经在现场安装西基台基础桩。同样重要的是,这种替代方案的安装时间最短,这是另一个关键因素,因为缅因州交通部(MaineDOT)制定的设计建造项目进度表非常激进。 MaineDOT以前未使用加固桩进行边坡稳定,但是该技术已成功用于美国以外的项目。使用振动锤在四天内总共安装了32个HP 12×53桩,以稳定西进路。这种具有成本效益和创新性的方法在这个540万美元的项目成功授予设计建造团队的过程中发挥了作用。

著录项

获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号