The Port of Alaska is modernizing its facilities through the Port of Alaska Modernization Program (PAMP). An initial step in the program was implementation of a test pile project (TPP), which involved installation of ten 200-foot long by 48-inch diameter, 1-inch wall, steel pipe piles. The TPP replicated the concept pile design and marine permit conditions. The project included (1) monitoring response of each pile during initial installation and 13 to 38 days after initial pile installation with a pile driving analyzer (PDA) and (2) evaluating the performance of two types of underwater noise attenuation systems (NAS). Key observations from the TPP included doubling of pile capacity for the setup periods, the absence of soil-plug formation during initial driving and restrike, and appreciable decreases in underwater noise from the use of the NAS. This paper summarizes background for and results of the test pile project.
机译:阿拉斯加港正在通过阿拉斯加现代化计划(PAMP)的港口现代化其设施。该程序的初始步骤是实施测试桩工程(TPP),该项目涉及安装10200英尺长的48英寸直径,1英寸1英寸的钢管桩。 TPP复制了概念桩设计和海洋许可条件。该项目包括(1)初始安装期间每桩的监测响应,初始桩安装后的13至38天,用桩驱动分析仪(PDA)和(2)评估两种类型的水下噪声衰减系统(NAS)的性能。来自TPP的关键观察包括桩容量的加倍,用于设置周期,初始驾驶和初始驾驶期间的土壤插头形成,并且来自使用NAS的水下噪声的明显降低。本文总结了测试桩项目的背景和结果。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号