TRACE/PARCS ANALYSIS OF FULL ISOLATION STARTUP TEST FOR LUNGMENABWR

机译:LungmenabWR完全隔离启动测试的TRACE / PARCS分析

获取原文

摘要

TRACE/PARCS coupling model of Lungmen NPP has been used to analyze the full isolation startup test, defined as a simultaneous full closure of all MSIVs (Main Steamline Isolation Valve). In this analysis, the full closure time of MSIVs was varied by 2 sec, 3sec (base), and 4 sec. As MSIV was closed to 90% full open position, a reactor power scram signal was initiated. For each of MSIV full closure time, the delayed time of scram signal to the start of control rod insertion was varied by base 0.09 sec, 0.04 sec, and 0.14 sec. Because of MSIVs closure, the increasing reactor dome pressure reached the setpoint of relief valves (RVs) and caused RVs to open. The 4 reactor internal pumps (RIPs) not connected to the M/G sets tripped and were runback to minimum pump speed when water level dropped to L3. The 6 RIPs connected to the M/G sets tripped if low water level (L2) or high reactor dome pressure (1140 psia) had been reached. Those important thermal parameters with various MSIV full closure times (2, 3, and 4sec) and various reactor scram signal delay times (0.09, 0.04, and 0.14 sec) are compared and shown in this paper.
机译:龙门NPP的TRACE / PARCS耦合模型已用于分析完全隔离启动测试,定义为所有MSIV(主蒸汽管线隔离阀)同时完全关闭。在此分析中,MSIV的完全关闭时间变化了2秒,3秒(基本)和4秒。当MSIV关闭到90%全开位置时,启动了反应堆功率扰动信号。对于每个MSIV完全关闭时间,scram信号到开始插入控制杆的延迟时间以0.09 sec,0.04 sec和0.14 sec为基础变化。由于MSIV的关闭,增加的反应堆圆顶压力达到了安全阀(RVs)的设定点,并导致RVs打开。当水位降至L3时,未连接到M / G装置的4个反应堆内部泵(RIP)跳闸,并退回至最小泵速。如果已达到低水位(L2)或高反应堆圆顶压力(1140 psia),则与M / G装置连接的6个RIP跳闸。比较并显示了具有各种MSIV完全关闭时间(2、3和4秒)和各种反应堆紧急信号延迟时间(0.09、0.04和0.14秒)的那些重要的热参数。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号