AN I/I PROGRAM CASE HISTORY: NASHVILLE REMOVES 3.6 BILLION GALLONS OF I/I 137 SSOs

机译:I / I程序案例的历史:NASHVILLE删除了36亿加仑I / I和137个SSO

获取原文

摘要

The Nashville Overflow Abatement Program (NOAP) uses trenchless sewer lining with rehabilitation of service laterals and manholes as its principal rehabilitation technique. This is called a "total system approach" and is a major factor in the reduction of I/I and the subsequent elimination of overflows. From 1991 through 2007, the NOAP completed about 324 miles of sewer rehabilitation projects. About 80% of this work used cured-in-place pipe (CIPP) and about 12% used fold-and-form pipe (FF) lining products, (the balance used replacement). NOAP rehabilitation projects have also renewed over 5,000 service laterals. Defective sewer laterals may contribute 20%-25% of system I/I and must be repaired in conjunction with work on adjacent public sewers to halt I/I migration. Manhole rehabilitation was included to complete the total picture in the strategy to halt migration. To develop a database of objective measurements of sewer rehabilitation effectiveness, twenty-seven basin areas in the Nashville system were monitored and analyzed which included 94 miles of sewer lining or replacement. A cumulative annual I/I reduction of 3.6 billion gallons has been documented for these projects. The 27 projects represented about 30% of the rehabilitation work conducted through the program since 1991. The goal of the program is to reduce I/I by 50%. Linear regression analyses were used to predict the I/I expected from the selected design rainfall. After rehabilitation, the net results met or exceeded that goal for reduction of 24-hour and peak-hour I/I from the design, 5-year 24-hour storm (4.5-inches), and reduction of annual I/I. The Nashville program is one of the most successful and well-documented large-scale sewer rehabilitation programs in the United States. This paper is an update of information reported by Kurz, et al, in 2004.
机译:纳什维尔溢流消除计划(NOAP)使用无挖沟下水道衬砌以及服务支管和人孔的修复作为其主要修复技术。这称为“全系统方法”,是减少I / I和随后消除溢出的主要因素。从1991年到2007年,NOAP完成了约324英里的下水道修复项目。这项工作中约80%使用的是现场固化管(CIPP),约12%的使用的是折叠成型管(FF)衬里产品(其余部分用于替代)。 NOAP修复项目还更新了5,000多个服务分支。不良的下水道支管可能占系统I / I的20%-25%,必须与相邻公共下水道的工作一起进行修理,以阻止I / I迁移。沙井修复被包括在内,以全面遏制迁移战略。为了建立客观的下水道修复效果评估数据库,对纳什维尔系统中的27个流域进行了监测和分析,其中包括94英里的下水道衬砌或更换。这些项目的年度I / I累计减少量达到36亿加仑。自1991年以来,这27个项目约占该计划进行的修复工作的30%。该计划的目标是将I / I减少50%。使用线性回归分析来预测从所选设计降雨中获得的I / I。修复后,最终结果达到或超过了从设计中减少24小时和高峰小时I / I,5年24小时风暴(4.5英寸)并减少年度I / I的目标。纳什维尔计划是美国最成功且有据可查的大规模下水道修复计划之一。本文是Kurz等人在2004年报告的信息的更新。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号