【24h】

CSO Sediment Removal in an Urban Tributary

机译:CSO沉积物在城市支流中删除

获取原文

摘要

Background/Objectives. Combined sewer overflow (CSO) sediments had accumulated within the Hendrix Street Canal, creating mounds that became exposed during diurnal tidal events resulting in the generation of nuisance odors. To mitigate this situation, the New York City Department of Environmental Protection (NYCDEP) removed the sediment mounds to a depth of 2.5 feet below mean low water. The primary goals of the project were to identify dredging and dewatering methodologies to allow for the removal of CSO sediments that comply with regulatory guidance documents, minimize sediment resuspension, maximize solids capture and provide the selected contractor with a suitable staging area to perform the work. Approach/Activities. Based upon a bathymetric survey of the Canal, the CSO sediments that lie above the datum 2.5 feet below mean low water had accumulated within the uppermost 1,500 feet of the Canal. Chemical characterization of the CSO sediments to be removed indicated that the sediments are “Class C material; High contamination, Acutely Toxic to Aquatic Life”, in accordance with New York State Department of Environmental Conservation Guidance Series documents. Additionally, sediment cores taken within the Canal showed that contaminant concentrations increased with depth. Therefore an engineered sand and carbon isolation cap was required to protect the water quality within the Canal. Both hydraulic and mechanical dredging via a clamshell bucket was evaluated. In order to evaluate dewatering technologies, sediment samples were collected and bench scale tests conducted for plate and frame and belt filter presses as well as geobag technologies. Resultant filtrate from these dewatering technologies was also collected and analyzed to determine if they could be returned to the water column within the area of active dredging. Results/Lessons Learned. Hydraulic dredging with mechanical dewatering was selected to remove the CSO sediments from the head end of the Canal. Major construction challenges overcome during dredging and capping activities included modification to both the elutriate water clarification system and the process used for placement of the sand containment cap. The clarification system originally provided resulted in excessive suspended solids being returned to the Canal from the dewatering process. To mitigate this issue, a barge was added downstream of the dewatering system, to function as an intermediate clarifier in order to remove the fine grained organic material present in the dredged slurry. The contractor’s procedure for placing the sand cap was also modified after initial pilot testing indicated that the in-situ sediments remaining in the Canal after
机译:背景/目标。组合的下水道溢出(CSO)沉积物积累在Hendrix街道运河内,从昼夜潮汐事件期间创造了曝光的土堆,导致产生滋扰的气味。为了减轻这种情况,纽约市环保(NYCDEP)将沉积物堆积在低于平均水下2.5英尺的深度。该项目的主要目标是识别疏浚和脱水方法,以便去除符合监管指导文件的CSO沉积物,最大限度地减少沉积物重悬,最大化固体捕获,并为所选择的承包商提供合适的分期区域来执行工作。方法/活动。基于对运河的碱基测量,位于低于平均水的基础上方的CSO沉积物,该沉积物在均值低于平均水中累积在运河的最上面的1,500英尺内。除去的CSO沉积物的化学表征表明沉积物是“C类材料;高污染,毒性急性生命“,按照纽约国家环境保护指导系列文件。另外,在运河内采取的沉积物芯表明污染物浓度随深度而增加。因此,需要一种工程砂和碳隔离盖来保护运河内的水质。评价通过蛤壳桶的液压和机械脱落。为了评估脱水技术,收集了沉积物样品,并对板材和框架和带式过滤器压力机以及Geobag技术进行了台式试验。还收集和分析来自这些脱水技术的所得滤液,以确定它们是否可以在主动疏浚区域内返回到水柱。结果/经验教训。选择具有机械脱水的液压挖掘以从管道的头端中除去CSO沉积物。在疏浚和覆盖活动期间克服了主要的施工挑战包括对露天水澄清系统的修改和用于放置砂壳盖的过程。最初提供的澄清系统导致过量悬浮的固体从脱水过程中返回管道。为了减轻这个问题,将驳船添加到脱水系统的下游,用作中间澄清器,以除去疏浚浆料中存在的细粒有机材料。在初始试验检测后,承包商的放置砂帽的程序也被修改,表明在运河后剩余的原位沉积物

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号