首页> 外文会议>Grouting and Ground Treatment >Long-Distance Grouting, Materials and Methods Grouting Conference 2003
【24h】

Long-Distance Grouting, Materials and Methods Grouting Conference 2003

机译:2003年长距离灌浆,材料和方法灌浆会议

获取原文

摘要

An abandoned 1600-meter (mile-long) rock tunnel had to be completely filled with grout. The total tunnel volume was approximately 4500 cubic meters (6000 cubic yards). The tunnel was water-filled with access only at each end through narrow, 25-meter deep (80 ft), vertical shafts. Access for pumping was feasible only from one end of the tunnel, thereby requiring unusually long distances for pumping. Through an extensive laboratory testing and modeling program, different grouts were tested for suitability for this project. The ideal grout would have low viscosity, good stability and, after setting, low bleed, moderate strength and low permeability. Materials tested included cement-bentonite, cement-flyash and combinations including blast furnace slag cement. Data is presented on the various grout materials leading up to the choice of a cement-bentonite-slag cement blend as the optimal mix for the project. The unusual conditions at this project required the use of divers and remote-operated vehicles to inspect the tunnel and to place the initial cable that would allow grout pipes to be drawn into the tunnel. Each component of the grout system was engineered to provide adequate capacity to fill the tunnel in three to four days, working around the clock. A backup system using a sleeve pipe to provide secondary grout was devised and installed. The work in the field progressed more or less as planned, with a few unknowns cropping up to make for some difficult moments. As it turned out, the secondary grout line was necessary to complete the work. Grout samples were taken during the project for confirmation testing and borings were drilled into the tunnel after the work to verify that the tunnel was full. Data from this phase of the project are also presented. This project presented an unusual opportunity to plan and test components pre-construction. While there is no way to verify, the distances that the grout was pumped may represent some kind of record.
机译:一条废弃的1600米(一英里长)的岩石隧道必须完全充满水泥浆。隧道总体积约为4500立方米(6000立方码)。隧道充满水,仅两端通过狭窄的25米深(80英尺)垂直竖井进入。仅从隧道的一端进行抽水是可行的,因此需要非常长的抽水距离。通过广泛的实验室测试和建模程序,测试了不同的灌浆对该项目的适用性。理想的灌浆应具有低粘度,良好的稳定性,凝固后具有低渗出,中等强度和低渗透性。测试的材料包括水泥-膨润土,水泥-粉煤灰以及包括高炉矿渣水泥在内的组合。给出了各种灌浆材料的数据,最终选择了水泥-膨润土-矿渣水泥混合物作为该项目的最佳混合物。该项目的异常情况要求使用潜水员和遥控车辆来检查隧道,并放置最初的电缆,以便将灌浆管拉入隧道。灌浆系统的每个组件都经过精心设计,可全天候工作,在三到四天内提供足够的容量来填充隧道。设计并安装了使用套筒管提供二次灌浆的备用系统。该领域的工作或多或少按计划进行了,一些未知的事物冒出来,使一些艰难的时刻变得艰难。事实证明,辅助灌浆线是完成工作所必需的。在项目进行期间,对灌浆样品进行了确认测试,并在工作完成后在隧道中钻了钻孔,以确认隧道已满。还显示了该项目此阶段的数据。这个项目提供了一个难得的机会来计划和测试组件的施工前。虽然无法验证,但灌浆的距离可能代表某种记录。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号