The reinforcement for a precipice of 'Nikko Kegon fall' by anchoring from the inside shaft without surface structure

机译:从没有表面结构的内轴锚固来加固“日光华严坠落”的悬崖

获取原文

摘要

In recent it is pointed out that a precipice of "Nikko Kegon fall" became dangerous due to the toppling failure of overhanging part for both the prefectural waterfall viewing platform and chargeable water fall viewing platform. As a countermeasure all works were performed inside the precipice for the sake of safety for tourists. That is why rock anchoring method was chosen without surface structures on the precipice. This construction, finished on April 2001, consists of a horizontal shaft and two vertical shafts in the jointed rock masses. Under these circumstances the severe observational method was needed to keep the safe construction considering long-term stability of the precipice. In this paper, the design concept and construction method of rock anchoring, the observational method and the behavior of precipice of "Nikko Kegon fall" during construction are discussed.
机译:近来指出,由于县瀑布观景台和可充电瀑布观景台的悬垂部分的倒塌故障,“日光华严瀑布”的悬崖变得危险。作为对策,为了游客的安全,所有工作都在悬崖上进行。这就是为什么选择在岩石上没有表面结构的岩石锚固方法的原因。该工程于2001年4月完成,由一个水平节理井和两个垂直节理井组成,位于节理的岩体中。在这种情况下,考虑到悬崖的长期稳定性,需要采取严格的观测方法来保持安全施工。本文讨论了锚固的设计思想和施工方法,施工过程中“日光华严坠落”的观测方法和悬崖的行为。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号