Design, construction, and operation of a 1,200-GPM passive bioreactor for metal mine drainage

机译:1200-GPM金属矿山排水用被动式生物反应器的设计,建造和运行

获取原文

摘要

An active underground lead mine produces water having a pH of 8.0 with 0.4 to 0.6 mg/L of Pb and 0.18 mg/L of Zn. A full-scale 1,200 gpm capacity bioreactor system was designed and permitted based on a phased program of laboratory, bench and pilot scale bioreactor testing; it was constructed in mid-1996. The gravity flow system, covering a total surface area of about five acres (2 ha), is composed of a settling basin followed by two anaerobic bioreactors arranged in parallel which discharge into a rock filter polishing cell that is followed by a final aeration polishing pond. The primary lead removal mechanism is sulfate reduction/sulfide precipitation. The discharge has met stringent in-stream water quality requirements since its commissioning. The system was designed to last about 12 years, but estimates suggest a much longer life based on anticipated carbon consumption in the anaerobic cells.
机译:活跃的地下铅矿生产的pH值为8.0的水含有0.4至0.6 mg / L的Pb和0.18 mg / L的Zn。根据实验室,实验台和中试规模生物反应器测试的分阶段计划,设计并允许了一个满载的1,200 gpm容量的生物反应器系统;它建于1996年中。重力流系统占地总面积约5英亩(2公顷),由一个沉降池,两个平行布置的厌氧生物反应器组成,然后排入岩石过滤器抛光池,最后一个曝气抛光池。主要的除铅机理是硫酸盐还原/硫化物沉淀。自投产以来,排放满足严格的河内水质要求。该系统的设计寿命约为12年,但根据预期的厌氧细胞碳消耗量,估计寿命更长。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号