首页> 外文会议> >Program Update on the Development and Demonstration of a HTS Power Cable to Operate in the Long Island Power Authority Transmission Grid
【24h】

Program Update on the Development and Demonstration of a HTS Power Cable to Operate in the Long Island Power Authority Transmission Grid

机译:用于在长岛电力局输电网中运行的HTS电力电缆的开发和演示的程序更新

获取原文

摘要

The US Department of Energy is currently funding the design, development and demonstration of the first long length, transmission level voltage, cold dielectric, high temperature superconductor power cable. The cable is designed for permanent installation in the Long Island Power Authority (LIPA) grid and will be able to carry 574 MVA at a voltage of 138 KV. The project is led by American Superconductor and the team is comprised of Nexans, Air Liquide and LIPA. This paper will describe the goals of the project, an overview of the cable design, refrigeration system and site design. It will also include the statistics of the HTS wire manufactured for this project, the results of the qualification testing on a prototype 30 meter cable and the preparation work of the refrigerator system. The cable will be completed and put into service in the LIPA grid in 2007.
机译:美国能源部目前正在资助设计,开发和演示第一条长,传输级电压,冷电介质,高温超导体电力电缆。该电缆设计用于永久安装在长岛电力局(LIPA)电网中,并且能够在138 KV的电压下承载574 MVA。该项目由美国超导公司牵头,该团队由耐克森,液化空气和LIPA组成。本文将描述该项目的目标,电缆设计,制冷系统和现场设计的概述。它还将包括为该项目生产的高温超导电线的统计数据,对30米原型电缆进行资格测试的结果以及冰箱系统的准备工作。该电缆将于2007年完成并在LIPA电网中投入使用。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号