At approximately 5:48 a.m. on August 13, 1991, phase B of the main stepup transformers of Niagara Mohawk's Nine Mile Point Unit 2 (NMP2) Nuclear Power Plant experienced a failure resulting in degraded voltage in phase B of the electrical AC distribution system. The duration of the degraded voltage lasted 12 cycles, the time required to clear the fault and to fast transfer the house loads to alternate offsite sources. The protective relaying schemes accomplished this without any abnormalities. Due to the nature of the fault and its protection, the turbine tripped, resulting in an automatic reactor scram. However, during the first transfer under degraded voltage conditions, five nonsafety-related uninterruptible power supplies (UPSs) tripped. The tripping of these UPSs resulted in the loss of plant process computers, control room annunciation, and a significant portion of nonsafety-related instrumentation and control circuits. The events of that day and the effects of the tripping are described and analyzed here.
机译:1991年8月13日凌晨5:48,尼亚加拉莫霍克(Niagara Mohawk)的九英里点2号机组(NMP2)核电厂的主要升压变压器的B相经历故障,导致交流配电系统B相的电压下降。降压的持续时间持续了12个周期,这是清除故障并快速将房屋负载转移到备用场外电源所需的时间。保护性继电器方案可以做到这一点,而不会出现任何异常情况。由于故障的性质及其保护,涡轮机跳闸,从而导致自动反应堆急停。但是,在降压条件下的首次传输期间,五个与安全无关的不间断电源(UPS)跳闸。这些UPS的跳闸导致工厂过程计算机丢失,控制室报警以及大部分与安全无关的仪表和控制电路丢失。此处描述并分析了当天的事件和跳闸的影响。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号