首页> 外文会议> >A method for calculating the breakdown voltages of long air gaps in transmission lines: evaluation of the lightning performance of transmission lines using no shield wire
【24h】

A method for calculating the breakdown voltages of long air gaps in transmission lines: evaluation of the lightning performance of transmission lines using no shield wire

机译:一种计算传输线中长气隙击穿电压的方法:不使用屏蔽线评估传输线的雷电性能

获取原文

摘要

The possibility of abandoning the shield wire on EHV-UHV transmission lines has been examined. Insulation lengths required to obtain an acceptable lightning performance of lines have been determined. Experimental data indicate that unshielded lines can be built using conventional metal or ferroconcrete towers and lengthened insulator strings. However, the highest cost efficiency is achieved with towers made of insulating concrete or composite polymeric elements, since this substantially reduces the tower height and thus the consumption of materials.
机译:已经研究了放弃EHV-UHV传输线上的屏蔽线的可能性。已经确定了获得可接受的线路防雷性能所需的绝缘长度。实验数据表明,可以使用常规的金属或钢筋混凝土塔架和加长的绝缘子串来建造非屏蔽线。然而,由绝缘混凝土或复合聚合物元件制成的塔架实现了最高的成本效率,因为这大大降低了塔架的高度,从而降低了材料的消耗。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号