首页> 外文会议>ISOPE-2012;International offshore and polar engineering conference >A Case Study of LNG Unloading Arm Installation at Kochi Seashore
【24h】

A Case Study of LNG Unloading Arm Installation at Kochi Seashore

机译:高知海滨LNG卸装臂安装案例

获取原文

摘要

This study introduces the construction practice for the LNG (LiquefiedNatural Gas) unloading arm installation at Kochi Vypeen Island insouth India. The difficulties faced and solutions implemented provide avery practical reference to any similar maritime projects. The firstattempt to install unloading arms was suspended for 5.5 months due tounsteady sea condition when southwest monsoon swept the project site.Through a multi-companies teamwork building and brainstorming, aneffective solution using a spudded tidal barge was proposed andimplemented resulting in the installation being successfully completed.
机译:本研究介绍了印度南部高知维佩恩岛的LNG(液化天然气)卸载臂安装的施工实践。面临的困难和实施的解决方案为任何类似的海事项目提供了实际的参考。由于西南季风席卷项目现场,海面不稳定,首次尝试安装卸货臂的活动被暂停了5.5个月。通过多公司团队的建设和集思广益,提出了一种有效的解决方案,使用潮汐驳船进行了安装并得以实施,从而成功完成了安装。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号