Petrobras developed a new kind of anchoring device known as Torpedo. This is a steel pile of appropriate weight and shape that is launched in a free fall procedure to be used as fixed anchoring point by any type of floating unit. There are two Torpedoes, T-43 and T-98 weighing 43 and 98 metric tons respectively. On October 2002 T-43 was tested offshore Brazil in Campos Basin. The successful results approved and certified by Bureau Veritas, and the need for a feasible anchoring system for new Petrobras Units in deep water fields of Campos Basin led to the development of a Torpedo with High Holding Power. Petrobras FPSO P-50, a VLCC that is being converted with a spread-mooring configuration will be installed in Albacora Leste field in the second semester of 2004. Its mooring analysis showed that the required holding power for the mooring system would be very high. Drag embedment anchors option would require four big Anchor Handling Vessels for anchor tensioning operations at 1400 m water depth. For this purpose T-98 was designed and its field tests were completed in April 2003. This paper discusses T-98 design, building, tests and ABS certification for FPSO P-50.
机译:Petrobras开发了一种新型的锚定装置,称为Torpedo。这是一种具有适当重量和形状的钢桩,通过自由落体程序发射,可被任何类型的浮动装置用作固定锚点。有两枚鱼雷,分别是T-43和T-98,分别重43吨和98公吨。 2002年10月,T-43在坎波斯盆地的巴西近海进行了测试。必维国际检验集团(Bureau Veritas)批准并认证了成功的结果,以及在Campos盆地深水区为新型Petrobras装置安装可行的锚固系统的需要,导致了具有高抓地力的鱼雷的发展。 Petrobras FPSO P-50(VLCC)正在改型为扩展式系泊配置,将于2004年下半年安装在Albacora Leste油田。其系泊分析表明,系泊系统所需的保持力非常高。阻力埋入式锚固选项将需要四个大的锚固处理船,以在1400 m的水深处进行锚固张紧操作。为此,设计了T-98,并在2003年4月完成了现场测试。本文讨论了FPSO P-50的T-98设计,建造,测试和ABS认证。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号