Application and Operating Analysis of ABB Generator Breaker in Chencun Hydroelectric Generator Units

机译:ABB发电机断路器在陈村水轮发电机组的应用与运行分析。

获取原文
获取原文并翻译 | 示例

摘要

Datang Chencun hydroelectric power plant was built and operated/generated electricity in 1970. Because SN4-10G breaker of the No.1 generator of the plant was found many problems during long-term operation, HGI-2 (S) generator breaker of SF_6 was selected as the replacement by techno-economic analysis of replacing the type of generator breaker. Operating analysis of the new type breaker during the next five-year operation in the field indicates that HGI-2 (S) generator breaker has high reliability in operation, meets the need of hydro-plant of regulating peak load, clears the concealed trouble and improve the level of the plant safety operation in power system. At the same time this paper advancing some appropriately improved advice according to the secondary fault of breaker control circuit.
机译:大唐陈村水电站于1970年建成投产。由于长期运行中发现该厂1号发电机SN4-10G断路器存在许多问题,SF_6的HGI-2(S)发电机断路器通过技术经济分析来选择更换发电机断路器的类型。对该新型断路器的未来五年现场运行分析表明,HGI-2(S)发电机断路器具有较高的运行可靠性,满足调节峰值负荷的水电厂的需要,消除了隐患并提高电力系统工厂安全运行水平。同时,针对断路器控制电路的二次故障,提出了相应的改进建议。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号