Using the case of Qianqiu Mine, Yima Coal Mining Administration, theoretical analysis, laboratory physical simulation, and underground observation were performed to study the major parameters for fully mechanized sublevel caving mining method, including drawing spacing, drawing sequence, drawing numbers, and number of shields performing simultaneous drawing. The effects of those parameters on coal recovery and amount of waste rocks were also investigated. The optimal coal drawing technology for this case was obtained.