THE STUDY ON THE KEY TECHNOLOGY ISSUES OFCONSTRUCTION DIVERSION DESIGN FOR THE HIGH ARCH DAMOF GOUPI-TAN HYDROPOWER STATION ON WUJIANG RIVER

机译:乌江构皮滩水电站高拱坝施工导流设计关键技术问题的研究。

获取原文
获取原文并翻译 | 示例

摘要

Goupi-Tan Hydropower Station is located on Wujiang River in Yuqing County, GuizhournProvince. It is one of the series of hydropower stations in the middle reach of Wujiang River. The station isrnmade up of double-curvature arched dam, flood releasing structure, right bank underground powerhouse,rnleft bank third class vertical ship lift and vertical seepage proof curtain. The maximum height of dam isrn232.5m, and the installation capacity of generating station is 3000MW. Based on the characteristics of thernproject, the technology difficult problems were come up against during the construction diversion design. Itrnincludes diversion standard selection with adjusted flood flow by the upstream reservoir, the diversionrntunnel construction with large section in the soft rock area, high speed building RCC cofferdams, settingrnoutlet hole in the dam for later diversion stage, etc. The all-year diversion mode of RCC cofferdam blockrnwater and diversion tunnel release the flow is adopted for the initial stage. And the all-year diversion modernfor mid and later stage is the dam block water temporarily, release flow through bottom outlet, emptyingrnoutlet, sluice deep outlet, crest outlet and flood discharging tunnel. The Goupi-Tan Hydropower Stationrnbegan closure the river in November, 2004. The upper and lower RCC cofferdams were constructed fromrnFebruary to June in 2005.The water seepage of foundation ditch is little during cofferdam block water inrnflood season in 2005 and 2006.
机译:构皮滩水电站位于贵州省玉清县的乌江上。它是乌江中游系列水电站之一。该站由双曲拱坝,泄洪结构,右岸地下厂房,左岸三等竖式升船机和竖式防渗帷幕组成。大坝最大高度为232.5m,发电站安装容量为3000MW。根据工程的特点,在施工导流设计中遇到了技术难题。它包括上游水库调水流量的分流标准选择,软岩区大断面的分流隧道建设,高速碾压混凝土RCC围堰,大坝的出水孔设置,以便后期分流等。初期采用碾压混凝土围堰挡水和引水隧洞放水。而中后期的全年分流是大坝暂时堵水,通过底部出水口,排空出水口,水闸深部出水口,顶峰出水口和泄洪隧道释放水流。构皮滩水电站于2004年11月开始封堵河道。上,下碾压混凝土围堰于2005年2月至6月建成。2005年和2006年围堰块状注水季节,基坑的渗水很少。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号