Case study of deep excavation in existing underground structure of three-story basement and diaphragm wall

机译:三层地下室和地下连续墙地下结构深基坑工程研究

获取原文
获取原文并翻译 | 示例

摘要

In general, site size of an urban renovation case is small in Taipei. The difficulty of workabilityrnis added by the influence of the old building foundation on the to-be-constructed building foundation. This paperrnpresents a renovation case of a building project, 12-story high with a 3-story underground basement covering arearnof 583m~2 in Taipei. Perimeter of the planned site is about 80 m. The existing foundation and the diaphragm wallrnare 14.2mand 25min depth, respectively. In addition, the diaphragm wall thickness of this old building is 70 cm.rnThe new building foundation planned to set inside the existing diaphragm wall of the old building. New buildingrnis planned to excavate down to 21.5 m, with drilled shafts H414×405×18×28mm installed down to 34 m.rnThe new foundation had been constructed by incorporating with the old diaphragm wall, the new drilled shaftsrnand cylindrical soil improvement . In addition, combining the top-down and bottom-up construction proceduresrnwas used by taking advantage of the B3 slab of to-be-constructed building to connect existing diagram wall andrnthe new installed drilled shafts to complete the building project.
机译:一般来说,台北市的一个城市装修案例的场地面积很小。旧建筑基础对待建建筑基础的影响增加了可操作性的难度。本文介绍了台北市某建筑项目的改造案例,该案例为12层高,地下3层地下室,覆盖面积为583m〜2。规划场地的周长约为80 m。现有的地基和隔膜墙的深度分别为14.2和25分钟。此外,该老建筑的隔板墙厚度为70厘米。新建筑基础计划设置在老建筑的现有隔板墙内。计划开挖至21.5 m的新建筑,H414×405×18×28mm的钻杆安装至34 m.rn新的地基是结合旧的隔板墙,新的钻杆和圆柱形土壤改良而成的。此外,结合了自上而下和自下而上的施工程序,利用了待建建筑物的B3板来连接现有的图墙和新安装的钻孔井,从而完成了建筑项目。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号