首页> 外文会议>Collection systems conference >No One Wants It but Everyone Needs It - Building an 8.5 mgd Wastewater System for the 5-Billion Dollar Mile
【24h】

No One Wants It but Everyone Needs It - Building an 8.5 mgd Wastewater System for the 5-Billion Dollar Mile

机译:没有人想要,但每个人都需要-为50亿美元的里程建设8.5 mgd废水系统

获取原文

摘要

The Dallas-Fort Worth area has been growing at a rapid pace and the City of Frisco, located approximately 25 miles north of Dallas, is leading the growth. A 1-mile stretch along the Dallas North Tollway includes four mixed-use developments totaling $5 Billion in capital investments. This area has been coined 'The 5 Billion Dollar Mile.' These developments required a rapid response by the City to formulate a smart plan and to quickly build the needed wastewater infrastructure. This resulted in planning, designing, and building $13.5-million of wastewater infrastructure in 34-months. The 5 Billion Dollar Mile is all within an undeveloped area in the same wastewater basin. The density associated with the high-rise buildings exceeded the wastewater flows projected by the City. When the developers began to approach the City with conceptual plans, analysis quickly began to determine the existing wastewater systems limitations. The first step was to update the City's Info Works model with these new flows which revealed these flows far surpassed the system's capacity. This analysis revealed an interceptor currently under construction would be surcharged with the proposed flows from the denser developments. The first solution was to delineate the development into sub-basins to better convey the flow and maximize use of the existing system. This aided but an additional study showed that further improvements were required to adequately convey the anticipated flows of the four developments. As the development plans gained clarity, the need for additional conveyance became apparent. An 02.additional 11-mgd needed to be conveyed from the 5 Billion Dollar Mile to the City's Stewart Creek West Waste Water Treatment Plant (SCW WWTP). Several options were considered to upsize the existing system to accommodate the expected flows through the gravity system. The residential impact was deemed too great to parallel an existing interceptor through an established development, not to mention the capital and construction costs. Instead, two lift stations were proposed along opposite sides of the basin. The City agreed to provide the lift station and gravity improvements necessary to convey 8.5-mgd of the proposed flow while the second lift station would serve the remaining 2.5-mgd produced by a single development and would be the responsibility of that developer. The initial location of the City's 8.5-mgd lift station was north of the proposed developments at a convergence point in the existing gravity system. The City proposed to purchase a section of the property at the first site location with intentions to add a trailhead associated with the City's Master Parks and Trails System in addition to the wastewater facility. When negotiations began to stall, alternative sites had to be considered. The lift station location ultimately settled within the northeast boundary of one of the proposed developments. This was a good solution for the overall project but lead to some new engineering challenges. The location was approximately 25-feet higher in ground elevation than the original site, requiring adjustments to the hydraulic design. Because the lift station was now located on the development's site, the size and aesthetics of the facility became a high priority. The visual impact was minimized by including a building with facade matching the developer's high-end buildings. A single force main was proposed to convey flow from both lift stations to the SCW WWTP. The majority of the 16,000-feet of force main (18-inch diameter) is located within the median of a major 4-lane thoroughfare. The pipe installation utilizes open cut and trenchless methods. This alignment also crosses one of the busiest intersections in the City, with an average traffic count of 30,000 vehicles per day. The team had to develop a solution to cross the intersection with minimal disturbance. A 2,500-foot horizontal directional drill was chosen for the crossing. The drill was designed to avoid compounding horizontal and vertical drill radii, avoid existing utilities within the median, and to minimize pavement repair. The drill parallels an existing 12-inch reused pipeline that was previously constructed by horizontal directional drilling. Entry, exit, offset, and crossing of the previous drill were all considered with the design. This project was bid as two separate construction contracts totaling $13.5-million and is currently under construction. As developments continue to seek growing areas, municipalities are faced with the struggle of maximizing existing systems and incorporating capital improvements, often in an expedited schedule, to accommodate the additional wastewater capacity associated with the developments. Flexibility and communication between all stakeholders has never been more critical. The use of Info Works modeling software proved invaluable with the dynamic nature of the developments and their flow estimates. This paper will discuss the unique challenges of designing and constructing an 8.5-mgd lift station and force main in the heart of a 5-Billion Dollar development.
机译:达拉斯-沃思堡地区一直在快速增长,位于达拉斯以北约25英里的弗里斯科市正在引领增长。沿着达拉斯北收费公路延伸1英里,包括四个综合用途开发项目,总资本投资为50亿美元。该地区被称为“ 50亿美元里程”。这些事态发展要求纽约市迅速做出反应,以制定明智的计划并快速建立所需的废水基础设施。结果导致在34个月内规划,设计和建设了1,350万美元的废水基础设施。 50亿美元的里程都位于同一污水池的未开发区域内。与高层建筑相关的密度超过了纽约市预计的废水流量。当开发人员开始使用概念计划接近纽约市时,分析迅速开始确定现有废水系统的局限性。第一步是使用这些新流程更新纽约市的Info Works模型,这表明这些流程远远超出了系统的容量。该分析表明,正在建设中的拦截器将被稠密的开发项目所提议的流量所超载。第一个解决方案是将开发划分为子盆地,以更好地传达流程并最大程度地利用现有系统。这是有帮助的,但另外一项研究表明,需要进一步改进以充分传达四个开发项目的预期流量。随着开发计划的清晰化,对其他运输工具的需求变得显而易见。需要从50亿美元的英里中将02.11毫克的附加量输送到该市的Stewart Creek West废水处理厂(SCW WWTP)。考虑了几种选择来扩大现有系统的规模,以适应通过重力系统的预期流量。人们认为,对住宅的影响太大,无法通过既定的开发与现有的拦截器并行,更不用说基本建设成本了。取而代之的是,在盆地的相对两侧提出了两个提升站。纽约市同意提供升降台和重力改善,以输送8.5 mgd的拟议流量,而第二个升降台将为单个开发项目生产的剩余2.5 mgd提供服务,并由开发商负责。纽约市8.5 mgd提升站的初始位置位于拟议开发项目的北部,位于现有重力系统的汇合点。纽约市提议在第一个工地位置购买该物业的一部分,目的是在废水处理设施之外增加与纽约市主公园和步道系统相关的入口。当谈判开始陷入僵局时,必须考虑其他地点。升降机站的位置最终落在拟议开发项目之一的东北边界之内。对于整个项目而言,这是一个很好的解决方案,但会带来一些新的工程挑战。该位置的地面标高比原始位置高25英尺,因此需要对水力设计进行调整。由于升降机站现在位于开发地点,因此设施的大小和美观成为当务之急。通过包括外观与开发人员的高端建筑物相匹配的建筑物,将视觉影响降到最低。提出了一个单一的主力总管,以将流量从两个提升站输送到SCW污水处理厂。 16,000英尺的主力管(直径18英寸)中的大部分位于4车道通行的中线。管道安装采用明挖和非开挖方法。该路线还穿越了纽约市最繁忙的十字路口之一,平均每天有30,000辆车通过。团队不得不开发一种解决方案,以最小的干扰穿越十字路口。选择了2,500英尺的水平定向钻机进行穿越。钻头的设计避免了水平和垂直钻头半径的混合,避免了中位数内的现有设施,并最大程度地减少了路面维修。钻头与现有的12英寸重用管道平行,该管道先前是通过水平定向钻井建造的。设计中考虑了上一个钻头的进入,退出,偏移和交叉。该项目是作为两个单独的建设合同中标的,总价为1,350万美元,目前正在建设中。随着发展不断寻求增长的地区,市政当局面临着最大化现有系统和整合资本改进的斗争,通常是在迅速的进度中进行。,以适应与开发相关的额外废水处理能力。所有利益相关者之间的灵活性和沟通从未如此重要。实践证明,使用Info Works建模软件对开发的动态性质及其流量估算具有无价的作用。本文将讨论在50亿美元开发项目的核心中设计和建造8.5 mgd提升站和主力总管所面临的独特挑战。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号