The 18,498-ft long Pulaski Skyway between Newark and Jersey City, in New Jersey,comprises two contiguous structures, over the Passaic and Hackensack Rivers. Rehabilitation to extendits service life, mitigate functional deficiencies, and improve overall conditions and safety, is under way.The rehabilitation of the Pulaski calls for independent concrete shells cast around the existing piercolumns. The shells will be supported on deep foundations (drilled shafts and/or micropiles), built next tothe remaining concrete caissons. New reinforced concrete caps will span over the existing caissons andaround the existing columns. Soil-Structure-Interaction analysis demonstrated the influence of kinematiceffects on the seismic response and the subsequent design of piers, foundations, and rehabilitation of thetrusses.
机译:位于新泽西州纽瓦克和泽西市之间的18498英尺长的普拉斯基空中通道,在帕萨克河和哈肯萨克河上包括两个相连的建筑物。正在进行修复以延长使用寿命,减轻功能缺陷并改善总体状况和安全性。\ r \ nPulaski的修复工作要求在现有墩柱周围浇铸独立的混凝土壳。壳体将支撑在深层基础上(钻孔的井筒和/或微型桩),该基础建在其余混凝土沉箱附近。新的钢筋混凝土盖将覆盖现有的沉箱和周围的现有柱子。土-结构-相互作用分析证明了运动学效应对地震响应的影响,以及墩,基础的后续设计以及筋的修复。

著录项

获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号