1.A good plan begins with the end in mind for all affectedparties. The City benefited greatly by contracting with theCM early so they could work with the city and engineersduring design.2.Having the GMAX developed at 30-percent design achievedthe City’s goal to secure project funding early and gave themconfidence that the number was right.3.Frequent formal and informal communication is needed tokeep the design moving along to meet a tight schedule.4.The design engineers worked with the City & CM early toestablish the construction sequencing schedule, which drovedesign and bidding. Design items were prioritized to meetthe CM schedule.