首页> 外文会议>American Water Works Association 2007 membrane technology conference amp; exposition >From 0 to 100-MGD in 30 Months - How the San Diego County Water Authority is Implementing the Largest Ultrafiltration Membrane Water Treatment Plant at Twin Oaks Valley with the Design-Build-Operate Process
【24h】

From 0 to 100-MGD in 30 Months - How the San Diego County Water Authority is Implementing the Largest Ultrafiltration Membrane Water Treatment Plant at Twin Oaks Valley with the Design-Build-Operate Process

机译:在30个月内从0到100-MGD-圣地亚哥县水务局如何通过设计-建造-运营流程在Twin Oaks山谷实施最大的超滤膜水处理厂

获取原文
获取原文并翻译 | 示例

摘要

The San Diego County Water Authority (Water Authority) currently imports water from the Metropolitan Water District of Southern California to supply the needs of its 24 member agencies in San Diego County. The Water Authority has initiated the new Twin Oaks Valley Water Treatment Plant (TOVWTP) project as part of a $3.2 billion Capital Improvement Program to meet the immediate need for additional regional treatment capacity.rnThe facility is designed to produce a base flow of 100-MGD of high quality drinking water with submerged ultrafiltration (UF), ozone, biological carbon contactors and chloramination while addressing increasingly stringent drinking water regulations, greater consumer demand for aesthetically pleasing tap water and diminished source water quality.rnThis large-scale facility will establish industry benchmarks by incorporating technological innovation and automated process control to optimally leverage operations staffing and water quality monitoring, environmental value and sustainability (e.g., minimizing residuals & energy consumption), and addressing public concerns (taste and odor, preserve green space, reduce plant footprint & public impact). As such, TOVWTP will serve as a landmark facility that meets the Water Authority's drinking water needs while exerting minimal local impact.rnThis presentation will cover the unique design, construction and schedule issues associated with a large-capacity facility requiring uninterrupted production of 100-MGD of drinking water. A key project challenge is meeting a fast-track delivery schedule. CH2M HILL must design, permit, construct, and commission the facility in less than 30 months (by April 15,2008). Once commissioned, CH2M HILL will be responsible for operations for a period of 15 years.rnThis information will be of interest to municipalities, utilities, regulators, and consultants at all staff levels who are interested in how a large capacity, state-of-the art drinking water facility is implemented on a fast-track schedule using an alternative procurement method.
机译:圣地亚哥县水务局(水务局)目前从南加州大都市水区进口水,以满足圣地亚哥县24个成员机构的需求。美国水务局已启动新的双橡树谷水处理厂(TOVWTP)项目,作为一项32亿美元的资本改善计划的一部分,以满足对额外区域处理能力的紧迫需求。该设施旨在产生100-MGD的基本流量具有超浸入式超滤(UF),臭氧,生物碳接触器和加氯处理的高品质饮用水,同时解决了日益严格的饮用水法规,消费者对美观的自来水的需求增加以及源水水质下降的问题。这家大型工厂将建立行业基准通过整合技术创新和自动化过程控制以最佳地利用运营人员和水质监测,环境价值和可持续性(例如,最大限度地减少残留物和能源消耗),并解决公众关注的问题(味道和气味,保护绿色空间,减少工厂占地面积和公共场所)影响)。因此,TOVWTP将成为具有里程碑意义的设施,既能满足水务局的饮用水需求,又能将对当地的影响降到最低.rn本演讲将涵盖与需要不间断生产100-MGD的大容量设施相关的独特设计,建造和进度问题喝水。项目面临的关键挑战是如何满足快速交付的时间表。西图集团必须在不到30个月的时间内(到2008年4月15日)设计,许可,建造和调试该设施。一旦投入使用,西图集团将负责为期15年的运营。rn这些信息将对市政当局,公用事业,监管机构以及所有员工级别的顾问感兴趣,他们对大容量,最新状态感兴趣使用替代的采购方法,可以在快速的时间表上实施艺术饮用水设施。

著录项

相似文献

  • 外文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号