STARTUP AND OPERATION OF A LARGE WASTEWATER TREATMENT PLANT IN WARM CLIMATE AND UNDER MODIFIED CONDITIONS - A CASE STUDY

机译:改良条件下温暖气候下大型污水处理厂的启动和运行-案例研究

获取原文
获取原文并翻译 | 示例

摘要

This study summarizes the findings and lessons learned from the start up and operation of arnlarge wastewater treatment plant in warm climate under modified conditions. The treatmentrnworks comprise of a newly constructed sewage treatment plant located in the city of Dubai,rnU.A.E with an ultimate capacity of 300 Ml/d. The plant can be reviewed in three major parts;rni.) liquid stream, ii.) sludge stream and iii.) odor control stream all having the latest state ofrnthe art technology and related equipments. The challenge in starting up the plant was relatedrnto the fact that only 20% of the flow was available in the form of hauled sewage to be hauledrnfrom septic tanks located in various parts of the city and also from the nearby industry whichrnwas uncontrollable. Furthermore, some parts of the plant were not ready to be commissionedrnon the day of the planned startup not to mention that effluent irrigation main was not completernto receive the treated sewage effluent (TSE) from the plant. A comprehensive commissioningrnplan was implemented and followed during the startup which was tailored according to thernactual conditions. The plant commissioning was conducted in a phased sequence to cater forrnthe expected and unexpected changes related to the inlet conditions. Commissioning andrnoperation of the plant was carried for over 18 months with success considering thernchallenging and difficult conditions.
机译:这项研究总结了在变暖条件下在温暖气候下arnarn废水处理厂的启动和运行中的发现和经验教训。该处理厂由位于阿联酋迪拜市的新建污水处理厂组成,最终处理能力为300 Ml / d。该工厂可以分为三个主要部分; rni。)液流,ii。)污泥流和iii。)异味控制流,它们均具有最新的最新技术和相关设备。启动该工厂所面临的挑战与以下事实有关:只有20%的流量以拖运污水的形式从位于城市各地的化粪池以及附近无法控制的工业中被拖运。此外,工厂的某些部分尚未准备好在计划启动之日投入使用,更不用说污水灌溉主管尚未完成,无法从工厂接收处理后的污水(TSE)。在启动过程中实施并遵循了全面的调试计划,该计划是根据实际情况量身定制的。工厂调试是分阶段进行的,以应对与进水条件有关的预期和意外变化。考虑到恶劣的环境和艰难的条件,该厂的调试和运行进行了18个月以上,并取得了成功。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号