Kimberly Clark Australia (KCA) is in the early stages of a Lean transformation within their Millicent Mill. The introduction of Lean principles to a largely traditional manufacturing process has been on going for approximately 18 months. From an initial trial in a small low volume area of the mill the Lean programme is now being pushed out across the manufacturing and supply chains with many successes and some failures in its application.rnThis paper highlights the requirement to smooth and standardise the production schedule as the preliminary step in introducing a Lean programme.
机译:金伯利·克拉克澳大利亚分公司(KCA)处于Millicent工厂的精益转型初期。将精益原理引入很大程度上是传统的制造过程已经进行了大约18个月。精益计划从最初在工厂较小的小批量生产区域试行以来,现已在整个制造和供应链中推广,但在其应用中却取得了许多成功和失败。引入精益计划的第一步。