Live working methods for anchors replacement on 400kV OHL

机译:带电更换400kV OHL锚的工作方法

获取原文
获取原文并翻译 | 示例

摘要

The Romanian power grid was developed in the 60 and 70 and for that reason some major maintenance works should be done from time to time on the OHL. The mechanical condition of the lines has to be improved by replacing the tower anchors. One of the main concerns in the current strategy CNTEE TRANSELECTRICA S.A. is to ensure a reliable and economical operation of power grids. Higher requirements for safe operation of transmission lines, problems on their deenergising for repairs, led to the necessity of elaboration of new maintenance methods, mainly Live Maintenance technology. Using live maintenance for replacing the anchors some working conditions (weather conditions, risk analysis, distances) should be carefully considered. Working preparation is very important and following Romanian regulations, technical and safety procedures had to be designed and applied.
机译:罗马尼亚电网是在60和70年代开发的,因此,不时应在OHL上进行一些重要的维护工作。必须通过更换塔锚来改善管线的机械状况。当前策略CNTEE TRANSELECTRICA S.A.的主要关注之一是确保电网的可靠和经济运行。对输电线路安全操作的更高要求,维修中断电的问题,导致需要制定新的维护方法,主要是实时维护技术。使用现场维护来更换锚固件时,应仔细考虑一些工作条件(天气条件,风险分析,距离)。工作准备非常重要,必须遵循罗马尼亚法规,设计和应用技术和安全程序。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号