Project scheduling is an important process within project management, providing an estimation regarding the duration of the project. Completion within the estimated duration is considered a crucial project success factor. In this concept, simulation is a valuable tool which overcomes most of the disadvantages of deterministic scheduling approaches and allowing a realistic modelling of project activity network and project duration. However, the quality of the results produced through simulation depends on the quality of the input data. This paper focuses on the identification of appropriate input data presenting an approach based on the acquisition of experts' knowledge through interviews and questionnaires.
机译:项目计划是项目管理中的重要过程,它提供有关项目持续时间的估计。预计工期内的完工被认为是至关重要的项目成功因素。在这种概念下,模拟是一种有价值的工具,它可以克服确定性调度方法的大多数缺点,并可以对项目活动网络和项目工期进行逼真的建模。但是,通过仿真产生的结果的质量取决于输入数据的质量。本文着重于确定适当的输入数据,提出了一种基于通过访谈和问卷调查获取专家知识的方法。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号