摘要

At Glan Llyn an unusual cluster of sinkholes in the glacial drift which overlies Lower Carboniferous Limestone poses recurring difficulties for design, construction and maintenance of the A55 North Wales Coast Road. The cluster comprises 51 sinkholes within 35 ha and prompted concern about the possible existence of larger, deeper cave systems and cavities lacking surface expression that might cause a potential collapse problem within the areas of highway construction. Comprehensive geological investigations carried out to characterize the foundation conditions included boreholes, geophysics, probe drillholes, trial pits and borehole photography. Subsurface studies failed to disclose cavernous openings in the limestone but revealed instead dissolution-enlarged joints and fractures forming an integrated network and generally infilled with loose clay. The glacial sediment cover consists of stiff clays and medium dense sand and gravel, however, in the vicinity of sinkholes, much weaker strata have developed due to disturbance effects. Highway design and construction incorporated a number of mitigating measures including geological surveillance of earthworks, excavation and infilling of identified sinkholes and geotextile reinforcement of the affected stretch of highway. Regular monitoring is carried out to check the structural integrity of the carriageway and ensure public safety. Early warning signs of failure have been detected at two sites and appropriate action taken.
机译:在格兰兰(Glan Llyn),冰川漂移中不寻常的一堆坑洞覆盖在较低的石炭系石灰岩上,给北威尔士A55海岸路的设计,建造和维护带来了反复的困难。该集群在35公顷内包括51个污水坑,这引发了人们的担忧,即可能存在更大,更深的洞穴系统以及缺少表面表情的空腔,这可能会在高速公路建设区域内引起潜在的坍塌问题。为表征基础条件而进行的综合地质调查包括钻孔,地球物理学,探测钻孔,试验坑和钻孔照相。地下研究未能揭示石灰岩中的海绵状开口,但揭示出溶蚀扩大的节理和裂缝形成了一个完整的网络,并通常充满了松散的粘土。冰川沉积物覆盖物由坚硬的粘土和中等密度的沙子和砾石组成,但是,在水坑附近,由于扰动作用,已形成了较弱的地层。高速公路的设计和施工采用了许多缓解措施,包括对土方工程进行地质监测,对确定的下沉坑进行挖掘和填筑以及对受影响的高速公路段进行土工布加固。定期进行监测以检查车道的结构完整性并确保公共安全。已在两个地点检测到故障的预警信号,并采取了适当的措施。

著录项

相似文献

  • 外文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号