Work done and work to come: Taparko-Bouroum Gold Project, Burkina Faso

机译:已完成的工作和将要完成的工作:布基纳法索Taparko-Bouroum金矿项目

获取原文
获取原文并翻译 | 示例
           

摘要

Engineering design was largely completed, with minor work still required on electrical, instrumentation and piping. Pre-stripping of the 3/5 and G/T pits was completed and 150 000 tonnes of soft ore was mined and stockpiled. All mining equipment (two 85 t shovels, nine 53 t trucks, two loaders, one drill and two bulldozers) were on site and fully operational. Foundations were poured for all major installations. The mill building steelwork was fabricated and delivered onsite. The ball mill components were refurbished and delivered. The CIL tanks were assembled and painted, and installation of tank-top steelwork commenced.
机译:工程设计已基本完成,在电气,仪表和管道方面仍需少量工作。完成了3/5和G / T矿坑的预剥离,并开采和储存了15万吨软矿石。所有采矿设备(两台85吨的铁铲,九辆53吨的卡车,两台装载机,一台钻机和两台推土机)均在现场并已全面投入使用。为所有主要装置浇筑了基础。轧钢厂的钢结构是现场制造和交付的。球磨机组件进行了翻新和交付。 CIL储罐进行了组装和涂漆,并开始安装罐顶钢结构。

著录项

  • 来源
    《African Mining》 |2007年第3期|共3页
  • 作者

  • 作者单位
  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类 矿业工程;
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号