首页> 外文会议>International Conference on Engineering Research and Development >Power Distribution in Lagos Metropolis: Assessment of 132kv Network Capacity
【24h】

Power Distribution in Lagos Metropolis: Assessment of 132kv Network Capacity

机译:Lagos Metropolis的配电:评估132kV网络容量

获取原文

摘要

In this study, Lagos power distribution network at sub-transmission voltage (132 kV) was modeled and assessed. This is very relevant for the planning of effective electricity supply to the economic capital. The expected power demand of the metropolis was determined and the normal mode parameters computed for numerical analysis. The study was done for two scenarios: unilateral and multilateral injection of power into the network, using matrix algebra of mode linear equations by current balance. Analyses of results show that the total capacity of existing 330 kV/132 kV injection sub-stations is 1.71 GVA. The apparent power required to feed Lagos metropolitan 132 kV network is about 2.5 GVA (at 0.89 power factor), when power is injected through all the 330kV/132 kV injection substations. However, power transferred in the network lines is only 0.93 GVA at 0.9 power factor and at 97.4% efficiency. The power transfer capacity of the132 kV network lines alone is adequate when all injection stations simultaneously supply electricity. Any condition (emergency or otherwise) allowing only unilateral in-feed option at 132 kV, will lead to inadmissible voltage drops and overload conditions of lines unless drastic load shedding measure is applied. The total capacity of 330 kV/132 kV injection substations is inadequate by about 0.74 GVA (29%). The total power required cannot be met by existing local thermal station of about 1.32 GVA maximum; the generating capacity development of Lagos should be looked into critically.
机译:在本研究中,模拟和评估子传输电压(132kV)的LAGOS配电网络。这对于对经济资本的有效电力供应规划非常相关。确定了大都市的预期电力需求,并且计算了用于数值分析的正常模式参数。这项研究是为两种情况完成的:使用当前平衡,使用模式线性方程的矩阵代数来进行两种情况:单侧和多边的电力进入网络。结果分析表明,现有330 kV / 132 kV注射子站的总容量为1.71 GVA。当通过所有330kV / 132 kV注入变电站注入电源时,馈送拉各斯大都市132 kV网络所需的表观电源约为2.5 GVA(以0.89功率因数)。但是,在网络线路中传输的功率仅为0.9功率因数,效率为97.4%。当所有注射站同时供电时,单独的132 kV网络线的电力传输容量是足够的。除非施加激烈的载荷脱落措施,否则任何条件(紧急情况或其他方式)允许在132 kV下允许单侧供进食选项,将导致不允许的电压下降和线的过载条件。 330 kV / 132 kV注射变电站的总容量不足约0.74 gva(29%)。现有的本地热站最大值的现有局部热站不能满足所需的总功率;应批判性地调查拉各斯的发电能力开发。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号