摘要

In the method for producing an underground structure, preferably a tunnel, with little earth cover under railway tracks or the like, the individual concreted structure or tunnel sections are advanced in the timed shifting process after their production. In order to prevent movements in the covering earth and the railway tracks during the digging-out of the earth at the local face and during the advancing of the tunnel sections, the rails, together with the sleepers and ballast foundation, are removed in sections. In a dug-out, flat pit is installed a covering reinforced concrete slab, onto which the ballast bed and the track skeleton are mounted again. The same procedure is followed in neighbouring areas and the reinforced concrete slab has further reinforced concrete slabs concreted onto it until the region through which a tunnel is to be driven is overlapped by a continuous concrete slab. After this concrete slab, which forms a securing means for the track, has been erected, the tunnel sections are advanced underneath said slab. IMAGE
机译:在用于制造地下结构,优选地是隧道的方法中,该地下结构优选地在铁路轨道或类似物之下几乎没有地被覆盖物,各个混凝土结构或隧道部分在其生产之后的定时平移过程中前进。为了防止在局部面挖土时以及在隧道段前进期间在覆盖土和铁路轨道中发生运动,将铁路段以及轨枕和道ast基础一起拆除。在挖出的平坑中,安装了一块覆盖钢筋混凝土板,在其上又安装了道ast床和轨道骨架。在邻近区域遵循相同的步骤,钢筋混凝土板将混凝土进一步浇筑在混凝土板上,直到要驱动隧道的区域被连续的混凝土板覆盖。在竖立形成用于轨道的固定装置的混凝土板之后,将隧道段推进到所述板下方。 <图像>

著录项

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号