首页> 外国专利> Method for constructing face slab of concrete face rockfill dam

Method for constructing face slab of concrete face rockfill dam

机译:混凝土面板堆石坝面板施工方法

摘要

PURPOSE: A construction method of a cut-off wall of a concrete surface cut-off wall type rockfill dam is provided to obtain safety and reduce construction periods by simultaneously unloading and assembling a vertical reinforcing bar in a longitudinal direction of a truck. CONSTITUTION: An upper rail and a slip form winch working vehicle(210) are installed on the top of a dam. Asphalt emulsion(241) is coated on the surface of a cut-off wall, and a horizontal reinforcing bar(240H) and a vertical reinforcing bar(240V) are arranged and are assembled. A rail guiding the slip form and a side form is installed. Concrete of the cut-off wall is placed by using the slip form. The vertical reinforcing bar is longitudinally unloaded from a vertical reinforcing bar truck(242). The horizontal reinforcing bar is transversely unloaded from a horizontal reinforcing bar truck(260). The upper part of the vertical reinforcing bar truck is connected to a slip form winch working vehicle by a rope, and the lower part is connected to a crane.
机译:目的:提供一种混凝土表面防渗墙式堆石坝的防渗墙的施工方法,以通过在卡车的纵向上同时卸载和组装垂直钢筋来获得安全性并减少工期。组成:上部水坝和滑模绞车工作车(210)安装在大坝顶部。将沥青乳液(241)涂覆在防渗墙的表面上,并布置并组装水平钢筋(240H)和垂直钢筋(240V)。安装了导向滑模和侧模的导轨。隔断墙的混凝土通过使用滑模放置。竖直钢筋从竖直钢筋卡车(242)纵向卸载。水平钢筋从水平钢筋卡车(260)横向卸载。立式钢筋运输车的上部通过绳索连接至滑模绞车工作车辆,下部与起重机连接。

著录项

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号