Helicopter final assembly critical path analysis

机译:直升机最终装配关键路径分析

摘要

Helicopter final assembly involves the installation of hundreds of components into the aircraft and takes thousands of man-hours. Meeting production targets such as total build days and total aircraft man-hours can be difficult when faced with challenges related to parts, workforce, and scheduling. A tool to identify key installations on which to focus efforts for maximum benefit can help improve performance to targets. The Critical Path Method was developed as a project management tool to aid in scheduling large and complex projects. Its application to manufacturing can provide the insights necessary to improve performance in an environment such as helicopter final assembly. This thesis provides a case study of helicopter final assembly. A critical path analysis is performed on the assembly process, using predecessor, duration, and resource data. The results of the analysis are used to draw conclusions about the system as a whole and to make recommendations to improve system performance.
机译:直升机的最终组装涉及将数百个组件安装到飞机上,并且需要数千个工时。当面对与零件,劳动力和日程安排有关的挑战时,要达到生产目标(例如总建造天数和飞机总工时)可能很困难。一种用于识别关键安装的工具,可以将精力集中在这些安装上,以最大程度地受益,从而有助于改善目标性能。关键路径法是作为项目管理工具开发的,可帮助安排大型复杂项目。它在制造中的应用可以提供必要的见解,以改善诸如直升机最终组装等环境中的性能。本文以直升机总装为例。使用前身,工期和资源数据对装配过程执行关键路径分析。分析结果可用于得出有关整个系统的结论,并提出改进系统性能的建议。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号