Improved construction of concrete viaducts with movable scaffolding systems in Spain

机译:改进了西班牙可移动脚手架系统的混凝土高架桥结构

代理获取
本网站仅为用户提供外文OA文献查询和代理获取服务,本网站没有原文。下单后我们将采用程序或人工为您竭诚获取高质量的原文,但由于OA文献来源多样且变更频繁,仍可能出现获取不到、文献不完整或与标题不符等情况,如果获取不到我们将提供退款服务。请知悉。

摘要

The current paper relates the state of the art of construction of viaducts with a movable scaffolding system (MSS). Two different procedures are introduced: the traditional sequence and the new sequence applied to some viaducts in Spain. The traditional sequence consists of two phases: first, concreting the bottom slab and webs, and then concreting the top slab of the deck. Once the first and second casting phases are completed, the total prestressing force is introduced. The new sequence consists of concreting a self-supporting core (i.e., the bottom slab, webs, and only a portion of the top slab). Once the self-supporting core has hardened, a partial prestressing force is introduced so that the scaffolding can be advanced to the next span; the central zone of the top slab is cast in a second phase. Both sequences are described here with their constructive peculiarities and issues.
机译:当前的论文涉及具有可移动脚手架系统(MSS)的高架桥建设的技术水平。介绍了两种不同的程序:适用于西班牙某些高架桥的传统序列和新序列。传统的顺序包括两个阶段:首先,浇筑甲板的底部平板和腹板,然后浇筑甲板的顶部平板。一旦第一和第二铸造阶段完成,就引入总预应力。新的顺序包括浇筑一个自支撑的岩心(即底部平板,腹板和顶部平板的仅一部分)。一旦自支撑芯变硬,便会引入部分预应力,以便使脚手架前进到下一个跨距;顶部平板的中央区域在第二阶段浇铸。这两个序列都以其建设性的特点和问题进行了描述。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
代理获取

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号