Task rescheduling model for resource disruption problem in unrelated parallel processor system

机译:无关并行处理器系统中资源中断问题的任务重新调度模型

代理获取
本网站仅为用户提供外文OA文献查询和代理获取服务,本网站没有原文。下单后我们将采用程序或人工为您竭诚获取高质量的原文,但由于OA文献来源多样且变更频繁,仍可能出现获取不到、文献不完整或与标题不符等情况,如果获取不到我们将提供退款服务。请知悉。

摘要

In this paper, we concentrate on the scheduling problem with interruption occurs in the parallel processor system. The situation happens when the availability of the unrelated parallel processors in the time slot decreases in certain time periods and its define as resource disruption. Our objective is to consider a recovery scheduling option for this issue to overcome the possibilities of having infeasibility of the original scheduling plan. Our approach for the recovery is task rescheduling which is to assign the tasks in the initial schedule plan to reflect the new restrictions. A recovery mixed integer linear programming model is proposed to solve the disruption problem. We also conduct a computational experiment using CPLEX 12.1 solver in AIMMS 3.10 software to analyze the performance of the model.
机译:在本文中,我们集中讨论并行处理器系统中发生中断的调度问题。当时隙中不相关的并行处理器的可用性在某些时间段内降低并且其定义为资源中断时,就会发生这种情况。我们的目标是考虑针对此问题的恢复计划选项,以克服原始计划计划不可行的可能性。我们的恢复方法是任务重新计划,即在初始计划计划中分配任务以反映新的限制。提出了一种恢复混合整数线性规划模型来解决扰动问题。我们还使用AIMMS 3.10软件中的CPLEX 12.1求解器进行了计算实验,以分析模型的性能。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
代理获取

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号