Resource-activity critical-path method for construction planning

机译:资源活动关键路径规划法

摘要

In this paper, a practical method is developed in an attempt to address the fundamental matters and limitations of existing methods for critical-path method (CPM) based resource scheduling, which are identified by reviewing the prior research in resource-constrained CPM scheduling and repetitive scheduling. The proposed method is called the resource-activity critical-path method (RACPM), in which (1) the dimension of resource in addition to activity and time is highlighted in project scheduling to seamlessly synchronize activity planning and resource planning; (2) the start/finish times and the floats are defined as resource-activity attributes based on the resource-technology combined precedence relationships; and (3) the "resource critical" issue that has long baffled the construction industry is clarified. The RACPM is applied to an example problem taken from the literature for illustrating the algorithm and comparing it with the existing method. A sample application of the proposed RACPM for planning a footbridge construction project is also given to demonstrate that practitioners can readily interpret and utilize a RACPM schedule by relating the RACPM to the classic CPM. The RACPM provides schedulers with a convenient vehicle for seamlessly integrating the technology/process perspective with the resource use perspective in construction planning. The effect on the project duration and activity floats of varied resource availability can be studied through running RACPM on different scenarios of resources. This potentially leads to an integrated scheduling and cost estimating process that will produce realistic schedules, estimates, and control budgets for construction.
机译:本文提出了一种实用的方法,以解决现有的基于关键路径法(CPM)的资源调度方法的基本问题和局限性,这些问题和局限性是通过回顾先前对资源受限的CPM调度和重复性研究的认识而确定的。排程。所提出的方法称为资源活动关键路径方法(RACPM),其中(1)在项目调度中突出显示除了活动和时间以外的资源维度,以无缝同步活动计划和资源计划; (2)基于资源技术组合的优先级关系,将开始/结束时间和浮动时间定义为资源-活动属性; (3)澄清了长期困扰建筑业的“资源紧要”问题。 RACPM应用于从文献中获取的示例问题,用于说明算法并将其与现有方法进行比较。还给出了拟议的RACPM用于规划人行天桥建设项目的示例应用程序,以证明从业人员可以通过将RACPM与经典CPM相关联来轻松地解释和利用RACPM进度表。 RACPM为调度员提供了一种方便的工具,可以将技术/过程视角与资源使用视角无缝集成到施工计划中。可以通过在不同资源场景下运行RACPM来研究对各种资源可用性对项目持续时间和活动浮动的影响。这潜在地导致了集成的进度计划和成本估算过程,该过程将生成实际的进度表,估算和控制施工预算。

著录项

  • 作者

    Lu M; Li H;

  • 作者单位
  • 年度 2003
  • 总页数
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类